Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 4 counties in Wisconsin: Milwaukee, Ozaukee, Washington, Waukesha. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| LABO0113-010 | ASBESTOS LABORER(ASBESTOS ABATEMENT [PREPARATION, REMOVAL, AND ENCAPSULATION OF HAZARDOUS MATERIALS FROM NON-MECHANICAL SYSTEMS]) | $40.48 | $23.92 |
| ASBE0019-001 | ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER(INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT) | $45.88 | $38.15 |
| SUWI2002-002 | ASBESTOS WORKER/HEAT AND FROST INSULATOR | $25.36 | $8.37 |
| BOIL0107-001 | BOILERMAKER(BOILERMAKER) | $46.52 | $34.63 |
| BRWI0008-001 | BRICKLAYER | $45.72 | $27.42 |
| CARP0231-001 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| CARPENTER & SOFT FLOOR LAYER(INCLUDING ACOUSTICAL WORK AND DRYWALL HANGING; EXCLUDING BATT INSULATION) |
| $45.46 |
| $31.52 |
| PLAS0599-004 | CEMENT MASON/CONCRETE FINISHER | $43.27 | $25.69 |
| ELEC0494-001 | ELECTRICIAN | $50.86 | $28.26 |
| ELEV0015-001 | ELEVATOR MECHANIC. FOOTNOTEA. PAID VACATION: 8% OF REGULAR BASIC FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY | $61.96 | $38.44 |
| PAIN1204-002 | GLAZIER | $49.79 | $25.15 |
| IRON0008-005 | IRONWORKER. PAID HOLIDAYSNEW YEAR'S DAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY & CHRISTMAS DAY | $47.52 | $33.67 |
| LABO0113-001 | LABORER(1) GENERAL LABORER (INCLUDING PLASTER TENDER) | $40.48 | $23.92 |
| LABO0113-001 | LABORER(3) JACKHAMMER OPERATOR, GUNNITE MACHINE MAN | $40.77 | $23.92 |
| LABO0113-001 | LABORER(2) AIR & ELECTRIC EQUIPMENT, MORTAR MIXER, SCAFFOLD BUILDER, ERECTOR, AND SWING STAGE | $40.62 | $23.92 |
| LABO0113-001 | LABORER(8) BARCO TAMPER | $41.97 | $23.92 |
| LABO0113-001 | LABORER(7) CAISSON WORK | $41.28 | $23.92 |
| LABO0113-001 | LABORER(6) NOZZLEMAN | $41.13 | $23.92 |
| LABO0113-001 | LABORER(5) CONSTRUCTION SPECIALIST | $41.09 | $23.92 |
| LABO0113-001 | LABORER(4) CAISSON WORKER - TOPMAN | $40.86 | $23.92 |
| SUWI2002-002 | LABORERSLANDSCAPE | $8.73 | $8.40 |
| SUWI2002-002 | LABORERSCONCRETE WORKER | $16.34 | $3.59 |
| BRWI0008-003 | MARBLE MASON | $45.72 | $27.42 |
| CARP2337-002 | MILLWRIGHT | $44.03 | $32.94 |
| PAIN0781-001 | PAINTERS(3) DRYWALL TAPER/FINISHER | $42.79 | $24.87 |
| PAIN0781-001 | PAINTERS(2) SPRAY & SANDBLAST | $43.19 | $24.87 |
| PAIN0781-001 | PAINTERS(1) BRUSH, ROLLER | $42.44 | $24.87 |
| ENGI0139-001 | PER HOUR PER 100 TONS OR 100 FT OF BOOM OVER 200 FT OR LIFTING CAPACITY OFCRANE OVER 200 TONS TO A MAXIMUM OF 300 TONS OR 300 FT. THEREAFTER AN INCREASE OF $0.01 PER FT OR TON, WHICHEVER IS GREATER. (KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WASHINGTON, AND WAUKESHA COUNTIES) HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER HOUR | $55.21 | $28.55 |
| CARP2337-008 | PILEDRIVERMAN | $44.39 | $34.79 |
| PLUM0601-001 | PIPEFITTER(INCLUDING HVAC WORK) | $58.92 | $31.34 |
| PLAS0599-005 | PLASTERER | $39.89 | $28.04 |
| PLUM0075-001 | PLUMBER(INCLUDING HVAC WORK) | $60.05 | $27.90 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 6 TAMPERS - COMPACTORS (RIDING TYPE); ASSISTANT ENGINEER; A-FRAMES AND WINCH TRUCKS; CONCRETE AUTO BREAKER; HYDROHAMMERS (SMALL); BROOMS AND SWEEPERS; HOIST (TUGGERS UNDER 5 TONS); BOATS (TUG, SAFETY, WORK BARGES, LAUNCH); SHOULDERING MACHINE OPERATOR; PRESTRESS MACHINES; SCREED OPERATOR; STONE CRUSHERS AND SCREENING PLANTS; SCREED OPERATORS (MILLING MACHINE), FARM OR INDUSTRIAL TRACTOR MOUNTED EQUIPMENT; POST HOLE DIGGER; FIREMAN (ASPHALT PLANTS); AIR COMPRESSORS OVER 400 CFM; GENERATORS, | $43.59 | $28.55 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 5 BACKFILLER; CONCRETE AUTO BREAKER (LARGE); CONCRETE FINISHING MACHINES (ROAD TYPE); RUBBER TIRED ROLLER; CONCRETE BATCH HOPPER; CONCRETE CONVEYOR SYSTEMS; GROUT PUMPS; CONCRETE MIXERS (14S OR OVER); SCREW TYPE PUMPS AND GYPSUM PUMPS; TRACTOR, BULLDOZER, END LOADER (UNDER 40 HP); TRENCHER (CHAIN TYPE, BUCKET UNDER 8 INCH); INDUSTRIAL LOCOMOTIVES; ROLLERS UNDER 5 TONS; STUMP GRINDER/CHIPPER (LARGE); TIMBER EQUIPMENT; FIREMEN (PILE DRIVERS AND DERRICKS); PERSONNEL HOIST, TELEHANDLER OVER 80 | $48.74 | $28.55 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 4 MATERIAL HOISTS; STACK HOISTS; HYDRAULIC BACKHOE (TRACTOR OR TRUCK MOUNTED); HYDRAULIC CRANE, 5 TONS OR UNDER (TRACTOR OR TRUCK MOUNTED); HOIST (TUGGERS 5 TONS & OVER); HYDRO-EXCAVATORS/DAYLIGHTERS; CONCRETE PUMPS ROTEC TYPE CONVEYORS; TRACTOR/BULLDOZER/END LOADER (OVER 40 HP); MOTOR PATROL; SCRAPER OPERATOR; SIDEBOOM; STRADDLE CARRIER; WELDER; BITUMINOUS PLANT AND PAVER OPERATOR; ROLLER OVER 5 TONS; RAIL LEVELING MACHINE (RAILROAD); TIE PLACER; TIE EXTRACTOR; TIE TAMPER; STONE LEVELER; | $52.72 | $28.55 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 3 BACKHOE (EXCAVATOR) UNDER 130,000 LBS;SELF-ERECTING TOWER CRANE 4000 LBS & UNDER LIFTING CAPACITY;TRAVELING CRANE (BRIDGE TYPE); SKID RIGS; DREDGE OPERATOR; MECHANIC; CONCRETE PAVER (OVER 27E); CONCRETE SPREADER AND DISTRIBUTOR; FORKLIFT/ TELEHANDLER (MACHINERY- MOVING / STEEL ERECTION); HYDRO BLASTER, 10,000 PSI AND OVER. (KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WASHINGTON, AND WAUKESHA COUNTIES) HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTIO | $54.21 | $28.55 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 2 CRANES, TOWER CRANES, PEDESTAL TOWER CRANES AND DERRICKS WITH OR WITHOUT ATTACHMENTS WITH A LIFTING CAPACITY OF 100 TONS OR LESS; OR CRANES, TOWER CRANES PORTABLE TOWER CRANES, PEDESTAL TOWER CRANES AND DERRICKS WITH BOOM, LEADSAND/OR JIB LENGTHS MEASURING 175 FEET OR LESS; BACKHOES (EXCAVATORS) 130,000 LBS AND OVER; CAISSON RIGS; PILE DRIVERS; BORING MACHINES (VERTICAL OR HORIZONTAL), VERSI-LIFT, TRI-LIFT, GANTRY 20,000 LBS & OVER. (KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WASHINGTON, AND W | $54.71 | $28.55 |
| ENGI0139-001 | POWER EQUIPMENT OPERATORGROUP 1 CRANES, TOWER CRANES, PEDESTAL TOWER CRANES AND DERRICKS WITH OR W/O ATTACHMENTS WITH A LIFTING CAPACITY OF OVER 100 TONS; OR CRANES, TOWER CRANES, PEDESTAL TOWER CRANES AND DERRICKS WITH BOOM, LEADS, AND/OR JIB LENGTHS MEASURING 176 FEET OR LONGER; SELF-ERECTING TOWER CRANES OVER 4000 LBS LIFTING CAPACITY; ALL CRANES WITH BOOM DOLLIES; BORING MACHINES (DIRECTIONAL); MASTER MECHANIC | $0.50 | ADDITIONAL |
| SUWI2002-002 | ROOFER | $18.01 | $3.28 |
| SHEE0018-001 | SHEET METAL WORKER(INCLUDING HVAC DUCT WORK AND TECHNICIANS) | $58.03 | $29.98 |
| ELEC0494-003 | SOUND & COMMUNICATIONS(TECHNICIAN) | $37.13 | $21.58 |
| ELEC0494-003 | SOUND & COMMUNICATIONS(INSTALLER) | $37.13 | $21.58 |
| SFWI0183-001 | SPRINKLER FITTER | $52.40 | $34.31 |
| BRWI0005-001 | TERRAZZO WORKER | $42.24 | $26.78 |
| BRWI0005-001 | TILE LAYER | $41.27 | $26.78 |
| SUWI2002-002 | TILE & MARBLE FINISHER | $13.89 | $7.43 |
| TEAM0662-003 | TRUCK DRIVER(3 OR MORE AXLES) | $39.72 | $28.70 |