Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 8 counties in Virginia: Amelia, Charles*, Goochland, Hanover, King William, New Kent, Powhatan, Prince George. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0024-006 | ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL(DUCT, PIPE & MECHANICAL SYSTEM INSULATION) A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY,THE DAY AFTER THANKSGIVING AND CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE REGULAR WORK DAY BEFORE AND AFTER THE PAID HOLIDAY | $40.77 | $20.17 |
| BOIL0045-003 | BOILERMAKER | $38.97 | $27.39 |
| SUVA2013-056 | BRICKLAYER | $20.00 | $1.00 |
| SUVA2013-056 | CARPENTER | $21.10 | $1.11 |
| SUVA2013-056 | CEMENT MASON/CONCRETE FINISHER | $17.23 | $0.00 |
| ELEC0666-004 | ELECTRICIAN(INCLUDES LOW VOLTAGE WIRING) |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $37.95 |
| $18.02 |
| ELEV0051-007 | ELEVATOR MECHANIC A. PAID HOLIDAYSNEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING AND CHRISTMAS DAY. B. VACATIONS: EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OR 6% OF BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF SERVICE AS VACATION PAY CREDIT | $51.39 | $38.44 |
| SUVA2013-056 | GLAZIER | $18.43 | $3.71 |
| SUVA2013-056 | HVAC MECHANIC(HVAC DUCT INSTALLATION ONLY) | $20.60 | $2.93 |
| IRON0028-007 | IRONWORKERSTRUCTURAL AND ORNAMENTAL | $31.00 | $18.28 |
| SUVA2013-056 | IRONWORKER, REINFORCING | $27.18 | $4.13 |
| SUVA2013-056 | LABORERMASON TENDER - CEMENT/CONCRETE | $12.96 | $3.12 |
| SUVA2013-056 | LABORERCOMMON OR GENERAL | $11.53 | $0.99 |
| SUVA2013-056 | LABORERMASON TENDER - BRICK | $13.41 | $3.15 |
| SUVA2013-056 | LABORERPIPELAYER | $12.28 | $1.96 |
| SUVA2013-056 | OPERATORROLLER | $16.25 | $4.88 |
| SUVA2013-056 | OPERATORBOBCAT/SKID STEER/SKID LOADER | $18.95 | $4.03 |
| SUVA2013-056 | OPERATORBULLDOZER | $17.50 | $0.00 |
| SUVA2013-056 | OPERATORFORKLIFT | $19.40 | $7.00 |
| SUVA2013-056 | OPERATORLOADER | $21.28 | $3.17 |
| SUVA2013-056 | OPERATORBACKHOE/EXCAVATOR/TRACKHOE | $19.74 | $1.43 |
| SUVA2013-056 | PAINTERSPRAY | $16.58 | $0.00 |
| SUVA2013-056 | PAINTER(BRUSH AND ROLLER) | $16.87 | $0.00 |
| PLUM0010-003 | PIPEFITTER(INCLUDES HVAC PIPE, UNIT AND TEMPERATURE CONTROLS INSTALLATIONS) | $33.25 | $19.47 |
| PLUM0010-003 | PLUMBER | $33.25 | $19.47 |
| ENGI0147-019 | POWER EQUIPMENT OPERATOR(CRANES UNDER 90 TONS) | $39.99 | $18.05 |
| ENGI0147-019 | POWER EQUIPMENT OPERATOR(CRANES 90 TONS & OVER CAPACITY; TOWER & CLIMBING CRANES WITH CONTROLS 100 FT. ABOVE GROUND) | $40.99 | $18.05 |
| SUVA2013-056 | ROOFER | $17.40 | $1.55 |
| SUVA2013-056 | SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $19.72 | $1.83 |
| SUVA2013-056 | SPRINKLER FITTER(FIRE SPRINKLERS) | $20.50 | $2.93 |
| SUVA2013-056 | TILE FINISHER | $23.40 | $0.00 |
| SUVA2013-056 | TILE SETTER | $27.80 | $10.25 |
| SUVA2013-056 | TRUCK DRIVERDUMP TRUCK | $14.88 | $0.00 |
| SUVA2013-056 | WATERPROOFER | $21.17 | $3.41 |