Revision 1 · modified May 18, 2026 · published May 18, 2026 · Heavy
Covers 1 county in Utah: Summit. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUUT2008-040 | CARPENTER, INCLUDES FORM WORK | $14.63 | $0.97 |
| SUUT2008-040 | CEMENT MASON/CONCRETE FINISHER | $17.08 | $3.14 |
| SUUT2008-040 | ELECTRICIAN | $23.74 | $7.64 |
| IRON0027-001 | IRONWORKER | $32.68 | $27.55 |
| LABO0295-006 | LABORERPOT TENDER AND SAND BLASTER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 |
| LABO0295-006 | LABORERCOMMON OR GENERAL, PIPELAYER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.59 | $8.65 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| LABO0295-015 |
| LABORER(5)HAND HELD DRILL |
| $21.65 |
| $8.65 |
| LABO0295-015 | LABORER(3) MASON TENDER (CEMENT/CONCRETE), HAND HELD SAW, JACKHAMMER, POWER SAW) | $20.85 | $8.65 |
| LABO0295-015 | LABORER(1)FLAGGER | $20.59 | $8.65 |
| LABO0295-038 | LABORER(1) COMMON OR GENERAL: EXCLUDING NATURAL GAS PIPELINE & WATER/SEWER LINE CONSTRUCTION | $20.59 | $8.65 |
| SUUT2008-040 | LABORERPIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.00 | $0.00 |
| SUUT2008-040 | LABORERLANDSCAPE | $7.25 | $0.00 |
| ELEC0057-002 | LINE CONSTRUCTIONLINEMAN | $58.83 | $21.21 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT: (1)MECHANIC-EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION | $41.71 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT: (3) BACKHOE/EXCAVATOR, FRONT END LOADER(OVER 5 CU.YDS.) | $39.01 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT ((2A)BLADE/GRADER) | $40.32 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT ((7) ROLLER(DIRT AND GRADE COMPACTION)) | $34.25 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT (6) SCREED | $36.55 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT: (5) ASPHALT ROLLER, BOBCAT/SKID LOADER, FRONT END LOADER(UNDER 2 CU. YDS.), OILER | $36.55 | $18.62 |
| ENGI0003-005 | OPERATORPOWER EQUIPMENT: (4) ASPHALT PAVER, BULLDOZER, FRONT END LOADER(2 TO 5 CU. YDS.), GRADE SETTER, OIL DISTRIBUTOR, SCRAPER | $37.79 | $18.62 |
| ENGI0003-056 | OPERATORPOWER EQUIPMENT OILER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $22.03 | $11.88 |
| ENGI0003-056 | OPERATORPOWER EQUIPMENT: BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, MECHANIC: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $35.68 | $17.57 |
| SUUT2008-040 | OPERATORTRACKHOE (EXCLUDING NATURAL GAS PIPELINE AND WATER/SEWER LINE CONSTRUCTION) | $19.98 | $0.00 |
| SUUT2008-040 | OPERATORCRANE | $28.97 | $9.40 |
| SUUT2008-040 | TRUCK DRIVER(EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.40 | $3.99 |
| TEAM0222-002 | TRUCK DRIVER ZONE 1GROUP 2 | $40.75 | $15.10 |
| TEAM0222-002 | TRUCK DRIVER ZONE 1GROUP 1 | $41.39 | $15.10 |
| TEAM0222-002 | TRUCK DRIVER ZONE 1GROUP 3 | $40.37 | $15.10 |
| TEAM0222-002 | TRUCK DRIVER ZONE 2GROUP 3 | $41.90 | $15.75 |
| TEAM0222-002 | TRUCK DRIVER ZONE 2GROUP 1 | $46.65 | $15.75 |
| TEAM0222-002 | TRUCK DRIVER ZONE 2GROUP 2 | $46.02 | $15.75 |
| SUUT2008-040 | WATER & SEWER LINESLABORER, COMMON OR GENERAL | $12.81 | $0.00 |
| SUUT2008-040 | WATER & SEWER LINESOPERATOR-BACKHOE/EXCAVATOR/TRACKHOE | $15.57 | $0.00 |