Pulling the wage determination…
Revision 3 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Pennsylvania: Franklin. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 3). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0023-007 | ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL(DUCT, PIPE & MECHANICAL SYSTEM INSULATION) (ASBESTOS ABATEMENT, REMOVAL FROM MECHANICAL SYSTEMS ONLY) | $40.00 | $29.81 |
| BOIL0013-008 | BOILERMAKER | $55.00 | $35.48 |
| BRPA0005-062 | BRICKLAYER(INCLUDING POINTING, CAULKING, AND CLEANING) | $33.99 | $16.87 |
| CARP0287-017 | CARPENTER(SCAFFOLD BUILDING ONLY) | $34.76 | $20.64 |
| CARP0900-017 | CARPENTER(DRYWALL HANGING AND METAL STUD INSTALLATION ONLY) | $34.76 | $20.64 |
| SUPA2011-048 | CARPENTER |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $37.73 |
| $4.59 |
| SUPA2011-048 | CARPENTER(FORM WORK ONLY) | $23.39 | $10.25 |
| SUPA2011-048 | CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND METALSTUD INSTALLATION, FORM WORK, AND SCAFFOLD BUILDING | $21.71 | $6.62 |
| SUPA2011-048 | CEMENT MASON/CONCRETE FINISHER | $26.33 | $10.14 |
| ELEC0143-011 | ELECTRICIAN(INCLUDES HVAC/TEMPERATURE CONTROLS INSTALLATION, AND LOW VOLTAGE WIRING; EXCLUDES INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS AND ALARM INSTALLATION) | $40.00 | $27.42 |
| ELEC0229-004 | ELECTRICIAN(ALARM INSTALLATION ONLY) | $40.31 | $23.93 |
| ELEC0743-011 | ELECTRICIAN(INSTALLATION OF COMMUNICATION AND SOUND SYSTEM) | $34.77 | $20.19 |
| ELEV0059-004 | ELEVATOR MECHANIC FOOTNOTESA. EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE AS VACATION PAY CREDIT, AND 6% OF BASIC HOURLY RATE FOR LESS THAN 5 YEARS OF SERVICE. B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY | $58.70 | $38.44 |
| SUPA2011-048 | FLOOR LAYERHARDWOOD FLOORS ONLY | $26.91 | $11.88 |
| SUPA2011-048 | FLOOR LAYERCARPET ONLY | $18.78 | $5.02 |
| SUPA2011-048 | FLOOR LAYERVINYL FLOORING ONLY | $19.71 | $5.94 |
| SUPA2011-048 | GLAZIER | $20.00 | $1.54 |
| IRON0404-022 | IRONWORKER, STRUCTURAL, REINFORCING AND ORNAMENTAL | $37.26 | $32.63 |
| LABO0373-001 | LABORER(ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, AND CEILINGS)) | $27.97 | $20.39 |
| LABO1180-013 | LABORER(CONCRETE WORKER; CONCRETE SAW (WALK BEHIND/HAND HELD)) | $25.01 | $19.48 |
| LABO1180-013 | LABORER(FORKLIFT (MASONRY WORK ONLY)) | $28.52 | $19.48 |
| LABO1180-013 | LABORER(JACK HAMMER; MASON TENDER-BRICK) | $27.02 | $19.48 |
| SUPA2011-048 | LABORERMASON TENDER - CEMENT/CONCRETE | $26.17 | $4.88 |
| SUPA2011-048 | LABORERCOMMON OR GENERAL | $18.09 | $8.34 |
| SUPA2011-048 | LABORERLANDSCAPE | $15.01 | $0.00 |
| CARP0443-003 | MILLWRIGHT | $43.00 | $23.44 |
| SUPA2011-048 | OPERATORGRADER/BLADE | $32.51 | $17.98 |
| SUPA2011-048 | OPERATORGRADALL | $32.70 | $18.43 |
| SUPA2011-048 | OPERATORDRILL | $25.58 | $17.07 |
| SUPA2011-048 | OPERATORBOBCAT/SKID STEER/SKID LOADER | $24.14 | $13.55 |
| SUPA2011-048 | OPERATORBACKHOE/EXCAVATOR/TRACKHOE | $23.73 | $7.50 |
| SUPA2011-048 | OPERATORLOADER | $27.05 | $14.52 |
| SUPA2011-048 | OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $30.39 | $15.05 |
| SUPA2011-048 | OPERATORROLLER | $30.39 | $13.72 |
| PAIN0057-037 | PAINTERBRUSH, ROLLER, AND SPRAY | $26.98 | $15.65 |
| CARP0274-003 | PILEDRIVERMAN | $43.13 | $23.42 |
| PLUM0520-021 | PIPEFITTER(INCLUDES HVAC PIPE AND HVAC UNIT INSTALLATION) | $41.36 | $29.45 |
| PLUM0520-020 | PLUMBER | $41.36 | $29.45 |
| ENGI0066-044 | POWER EQUIPMENT OPERATOR(PUMP) | $32.25 | $21.32 |
| ENGI0066-044 | POWER EQUIPMENT OPERATOR(MECHANIC) | $36.87 | $21.32 |
| ENGI0542-032 | POWER EQUIPMENT OPERATOR(OILER) | $39.42 | $29.30 |
| ENGI0542-032 | POWER EQUIPMENT OPERATOR(HOIST (WITH TWO TOWERS), FORKLIFT (20 FT AND OVER, EXCLUDES MASONRY WORK)) | $44.61 | $30.83 |
| ENGI0542-032 | POWER EQUIPMENT OPERATORCRANE | $47.14 | $31.58 |
| ENGI0542-032 | POWER EQUIPMENT OPERATOR(HOIST (SINGLE DRUM), FORKLIFT (UNDER 20 FT., EXCLUDES MASONRY WORK)) | $41.88 | $30.03 |
| SUPA2011-048 | ROOFERWATERPROOFING ONLY | $28.60 | $18.02 |
| SUPA2011-048 | ROOFER, EXCLUDES WATERPROOFING | $21.32 | $10.39 |
| SHEE0019-015 | SHEET METAL WORKERINCLUDES HVAC DUCT INSTALLATION FOOTNOTE: PAID HOLIDAY: ELECTION DAY | $43.09 | $42.52 |
| SFPA0669-004 | SPRINKLER FITTER(FIRE SPRINKLERS) | $49.75 | $30.26 |
| SUPA2011-048 | TILE FINISHER | $20.65 | $8.24 |
| SUPA2011-048 | TILE SETTER | $24.31 | $11.62 |
| SUPA2011-048 | TRUCK DRIVERDUMP TRUCK | $19.77 | $5.02 |