Revision 3 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Pennsylvania: Cambria. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 3). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0023-008 | ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL(DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $40.00 | $29.81 |
| BOIL0154-003 | BOILERMAKER | $48.28 | $33.17 |
| BRPA0009-044 | BRICKLAYER(INCLUDING POINTING, CAULKING, CLEANING) | $34.14 | $22.00 |
| CARP0423-007 | CARPENTER(SCAFFOLD BUILDING AND FLOOR LAYING-HARDWOOD ONLY) | $33.01 | $18.09 |
| CARP0423-008 | CARPENTER(INCLUDES ACOUSTICAL CEILING INSTALLATION, BATT INSULATION, DRYWALL HANGING, METAL STUD INSTALLATION, FLOOR LAYING-CARPET AND VINYL, FORM WORK AND GUTTER INSTALLATION; EXCLUDES SCAFFOLD BUILDING AND FLOOR LAYING-HARDWOOD FLOORS.) | $33.01 | $18.09 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| PLAS0526-015 |
| CEMENT MASON/CONCRETE FINISHER |
| $31.77 |
| $21.89 |
| ELEC0005-014 | ELECTRICIAN(INCLUDES ALARM INSTALLATION, INSTALLATION OF SOUND AND COMMUNICATION SYSTEM AND LOW VOLTAGE WIRING; EXCLUDES HVAC TEMPERATURE CONTROL INSTALLATION) | $49.11 | $36.79 |
| SUPA2011-038 | ELECTRICIAN(HVAC/TEMPERATURE CONTROLS INSTALLATION ONLY) | $34.86 | $18.55 |
| PAIN0751-002 | GLAZIER | $25.40 | $25.47 |
| IRON0003-022 | IRONWORKER(ORNAMENTAL, REINFORCING, RIGGER, STRUCTURAL) | $38.89 | $34.54 |
| LABO0125-005 | LABORER(MASON TENDER - CEMENT/CONCRETE) | $30.24 | $12.05 |
| LABO0824-002 | LABORERMASON TENDER-BRICK | $29.56 | $17.05 |
| SUPA2011-038 | LABORERCOMMON OR GENERAL | $17.53 | $10.02 |
| BRPA0009-044 | MASON - STONE | $34.14 | $22.00 |
| CARP0443-004 | MILLWRIGHT | $43.00 | $23.44 |
| SUPA2011-038 | OPERATORFORKLIFT, ALL TYPES | $23.69 | $13.13 |
| PAIN0057-035 | PAINTER(DRYWALL FINISHING/TAPING ONLY) | $32.39 | $23.26 |
| PAIN0057-035 | PAINTERBRUSH, ROLLER, AND SPRAY ONLY | $30.56 | $23.72 |
| PLUM0520-018 | PIPEFITTER | $41.36 | $29.45 |
| PLAS0526-025 | PLASTERER | $29.20 | $12.86 |
| PLUM0354-009 | PLUMBER(INDUSTRIAL) | $47.75 | $26.55 |
| SUPA2011-038 | PLUMBER(HVAC PIPE INSTALLATION ONLY) | $30.44 | $18.73 |
| SUPA2011-038 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION AND WORK ON INDUSTRIAL SITES | $30.14 | $18.83 |
| ENGI0066-041 | POWER EQUIPMENT OPERATORHOIST, PUMP | $29.70 | $21.32 |
| ENGI0066-041 | POWER EQUIPMENT OPERATOROILER | $29.70 | $21.32 |
| ENGI0066-041 | POWER EQUIPMENT OPERATORROLLER | $32.25 | $21.32 |
| ENGI0066-041 | POWER EQUIPMENT OPERATORBOBCAT/SKID STEER/SKID LOADER, DRILL, GRADALL, GRADER/BLADE, PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $36.87 | $21.32 |
| ENGI0066-041 | POWER EQUIPMENT OPERATORBACKHOE/EXCAVATOR/TRACKHOE, BULLDOZER, CRANE* LOADER, MECHANIC) *ADD TO CRANE RATE: BOOMS 101-150 JIBS- ADD $.75 BOOMS 151-200 JIBS- ADD $1.50 BOOMS 201-251 JIBS- ADD $2.25 | $36.87 | $21.32 |
| SUPA2011-038 | ROOFERWATERPROOFING ONLY | $29.50 | $21.10 |
| SUPA2011-038 | ROOFER, EXCLUDES WATERPROOFING | $33.50 | $20.66 |
| SHEE0012-012 | SHEET METAL WORKER(HVAC DUCT INSTALLATION ONLY) | $39.50 | $30.79 |
| SUPA2011-038 | SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $31.38 | $19.73 |
| BRPA0009-011 | TILE FINISHER | $28.76 | $17.16 |
| BRPA0009-011 | TILE SETTER | $35.64 | $21.63 |
| SUPA2011-038 | TRUCK DRIVERDUMP TRUCK | $23.36 | $7.60 |