Pulling the wage determination…
Revision 2 · modified May 18, 2026 · published May 18, 2026 · Residential
Covers 1 county in Pennsylvania: Mercer. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 2). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0002-004 | ASBESTOS WORKERS/INSULATOR(INCLUDES APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS & FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS) | $46.50 | $29.43 |
| BOIL0154-001 | BOILERMAKER | $48.28 | $33.17 |
| BRPA0009-013 | BRICKLAYER | $34.73 | $24.14 |
| CARP0268-004 | CARPENTERS | $23.23 | $11.40 |
| ELEC0712-004 | ELECTRICIAN | $27.15 | $16.72 |
| ELEV0006-001 | ELEVATOR MECHANICFOOTNOTE: A. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $61.07 |
| $38.44 |
| CARP1759-002 | FLOOR LAYERCARPET | $33.01 | $16.45 |
| IRON0207-001 | IRONWORKER(STRUCTURAL, ORNAMENTAL & REINFORCING) | $36.26 | $28.16 |
| LABO0964-003 | LABORER | $22.73 | $18.97 |
| CARP0443-004 | MILLWRIGHT | $43.00 | $23.44 |
| PAIN0057-017 | PAINTER(BRUSH AND ROLLER) | $30.56 | $23.72 |
| PLAS0526-021 | PLASTERER | $30.69 | $13.03 |
| PLUM0027-008 | PLUMBER AND STEAMFITTER | $23.75 | $15.30 |
| ENGI0066-012 | POWER EQUIPMENT OPERATORSCLASS I ASPHALT PAVER, ASPHALT ROLLER, ASPHALT PLANT OPERATOR, ATHEY LOADER, AUGER (TRUCK OR TRACTOR MOUNTED), AUTO GRADER (C.M.I. AND SIMILAR), BACKHOE (180' AND 360' SWING), BACK-FILLING MACHINE, BATCH PLANT, BULLDOZER, CABLE LAYER, CABLEWAY, CAISSON DRILL, CENTRAL MIX PLANT, COMPACTOR WITH BLADE, CONCRETE PUMP (ALL TYPES), OVER-HEAD CRANE, CRANE (CRAWLER OR TRUCK MOUNTED)*, TOWER CRANE (STATIONARY OR CLIMBING TYPE), ROUGH TERRAIN CRANE**, WAGON CRANE, CRUSHING AND/OR SCREENING PLANT, DERRICK | $31.05 | $15.75 |
| ENGI0066-012 | POWER EQUIPMENT OPERATORSCLASS II BALLAST REGULATOR, BOAT (MATERIAL OR PERSONNEL)(POWERED), BOILER, BORING MACHINE, COMPRESSOR (COMBINED WITH AIR TUGGER, AIR PUMP, GUNITE MACHINE, OR SAND BLASTER), CONCRETE BELT PLACER, CONCRETE SAW, CONVEYOR, CARRY CRANE, CRUSHING/SCREENING PLANTS, CURB BUILDER (SELF-PROPELLED), FORKLIFTS (RIDDEN OR SELF-PROPELLED), FORM LINE MACHINE, GENERATOR (OVER 5KW), GROUT PUMP, HEATERS, HOIST (MONORAIL, ROOF, ONE DRUM-REGARDLESS OF POWER USED), HUCK MACHINE (OR SIMILAR), HYDRAULIC JACK (SINGLE O | $27.36 | $15.75 |
| ENGI0066-012 | POWER EQUIPMENT OPERATORSCLASS III BRAKEMAN, DECK HAND, HELICOPTER SIGNALMAN, OILER*, ELEVATOR (ALTERATIONS & REMODELING COMMERCIAL BUILDINGS), * OILERS ON TRUCK CRANES: LESS THAN 50 TON SHALL RECEIVE $.10 OVER THE CLASS III BASE RATE; 50 TON UP TO 100 TON RATED CAPACITY SHALL BE PAID AN ADDITIONAL $.25 PER HOUR OVER THE CLASS III BASE RATE; 100 TON AND OVER SHALL BE PAID AN ADDITIONAL $1.00 PER HOUR OVER THE CLASS III BASE RATE. GENERAL NOTE: HAZARDOUS MATERIAL SITES LEVEL C & D RECEIVE $1.00 PER HOUR PREMIUM FOR ALL C | $25.64 | $15.75 |
| ROOF0071-003 | ROOFER | $29.81 | $18.76 |
| SHEE0033-002 | SHEET METAL WORKER | $28.03 | $18.92 |
| SFPA0669-001 | SPRINKLER FITTER | $49.75 | $28.96 |
| BRPA0009-013 | TERRAZZO WORKER/SETTER | $35.49 | $20.32 |
| BRPA0009-013 | TILE SETTER | $35.64 | $21.63 |