Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in New Jersey: Somerset. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0032-007 | ASBESTOS WORKER/HEAT & FROST INSULATORINCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET COUNTY (BOROUGHS OF BERNARDSVILLE AND BOUND BROOK; TOWNSHIP OF BRIDGEWATER; BOROUGH OF FAR HILLS; TOWNSHIP OF GREEN BROOK; BOROUGHS OF NORTH PLAINFIELD, PEAPACK-GLADSTONE, RARITAN, SOMERVILLE, SOUTH BOUND BR | $51.74 | $46.20 |
| ASBE0089-007 | ASBESTOS WORKER/HEAT & FROST INSULATORINCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET COUNTY (TOWNSHIPS OF BRANCHBURG, FRANKLIN, HILLSBOROUGH AND MONTGOMERY)) PAID HOLIDAYS: THE LAST DAY PRIOR TO THE CHRISTMAS AND NEW YEAR'S DAY OBSERVED HOLIDAY: 4 HRS. PAY | $55.80 | $40.80 |
| BRNJ0002-013 | BRICKLAYER WORK ON HIGH STACKS22% PER HOUR ADDITIONAL. | $45.20 | $33.26 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| CARP0006-009 | CARPENTERSCAFFOLD BUILDER THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER. | $57.42 | $34.17 |
| CARP0006-011 | CARPENTERINCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION | $57.42 | $34.17 |
| BRNJ0004-001 | CEMENT MASON | $49.60 | $37.96 |
| PAIN0711-018 | DRYWALL FINISHER/TAPER | $44.87 | $30.15 |
| ELEC0102-022 | ELECTRICIANINCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCE | $65.43 | $42.86 |
| ELEC0102-022 | ELECTRICIANCABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORT | $69.72 | $44.27 |
| ELEC0269-019 | ELECTRICIANINCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE))) | $61.84 | $40.32 |
| ELEC0456-007 | ELECTRICIANINCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UND | $55.85 | $39.79 |
| ELEC0456-007 | ELECTRICIANCABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND | $65.35 | $46.56 |
| ELEV0001-003 | ELEVATOR MECHANICALL OTHER WORK PAID NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS PAID A WORKER WHO HAS WORKED LESS THAN 5 YEARS: 4% OF HIS OR HER HOURLY RATE FOR ALL HOURS A WORKER WHO HAS WORKED 5 TO 10 YEARS: 6% OF HIS OR HER HOURLY RATE FOR ALL HOURS A WORKER WHO HAS WORKED 15 OR MORE YEARS: 8% OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED. | $57.01 | $27.61 |
| ELEV0001-003 | ELEVATOR MECHANICWORK ON THE ADDITION, REPLACEMENT, REFURBISHING OR RELOCATION OF CONTROL, DRIVE, GENERATING EQUIPMENT, HOISTWAY OR PIT EQUIPMENT, INCLUDING WORK INVOLVING A STRUCTURAL RISE IN THE ELEVATOR SHAFTS IN AN EXISTING BUILDING AND OTHER ELEVATOR WORK IN THE MACHINE ROOM, HOISTWAY OR PIT; ALSO, CHANGES IN DESIGN AND APPEARANCE OF BASIC ESCALATOR EQUIPMENT PAID NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY | $45.14 | $27.46 |
| PAIN0711-021 | GLAZIER WORK WELDING OR USING A CUTTING TORCH$1.00 PER HOUR WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL | $52.68 | $31.29 |
| IRON0011-010 | IRONWORKERSTRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (NORTHERN HALF OF COUNTY)) | $52.24 | $50.32 |
| IRON0011-010 | IRONWORKERREINFORCING (SOMERSET COUNTY (NORTHERN HALF OF COUNTY)) | $49.94 | $50.32 |
| IRON0399-018 | IRONWORKERSTRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)) | $54.24 | $38.40 |
| IRON0399-018 | IRONWORKERREINFORCING (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)) | $53.24 | $38.40 |
| LABO0008-001 | LABORERASBESTOS REMOVAL THE REMOVAL, ABATEMENT, ENCLOSURE AND DECONTAMINATION OF PERSONAL PROTECTIVE EQUIPMENT, CHEMICAL PROTECTIVE CLOTHING AND MACHINERY RELATING TO ASBESTOS AND/OR TOXIC AND HAZARDOUS WASTE OR MATERIALS WHICH SHALL INCLUDE BUT NOT NECESSARILY BE LIMITED TO: THE ERECTION, MOVING, SERVICING AND DISMANTLING OF ALL ENCLOSURES, SCAFFOLDING AND BARRICADES; THE OPERATION OF ALL TOOLS AND EQUIPMENT NORMALLY USED IN THE REMOVAL OR ABATEMENT OF ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR MATERIAL | $28.37 | $21.62 |
| LABO0077-002 | LABORERMASON TENDER: BRICK/CEMENT/CONCRETE | $36.50 | $30.22 |
| LABO0077-005 | LABORERASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL OPERATOR AND SCREEDMAN | $35.75 | $30.22 |
| CARP0715-007 | MILLWRIGHT WORK OF ERECTION AND DISMANTLING OF ELEVATORS AND TOWERS, SUCH ASCONCRETE CONVEYORS AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE OR OUTSIDE OF BUILDINGS: THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER | $58.84 | $35.06 |
| PAIN0711-020 | PAINTERPAPERHANGER | $45.55 | $29.86 |
| PAIN0711-020 | PAINTERBRUSH AND ROLLER | $45.55 | $29.86 |
| PAIN0711-020 | PAINTERSPRAY | $45.55 | $29.86 |
| PLUM0009-020 | PIPEFITTERINCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | $59.57 | $46.45 |
| PLUM0475-012 | PIPEFITTERINCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | $56.34 | $50.80 |
| PLAS0008-008 | PLASTERER | $38.37 | $31.64 |
| PLUM0009-020 | PLUMBEREXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | $59.57 | $46.45 |
| PLUM0024-011 | PLUMBEREXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | $62.09 | $45.05 |
| PLUM0009-020 | PLUMBER/PIPEFITTERSERVICE AND REPAIR (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | $46.23 | $29.23 |
| ENGI0825-020 | POWER EQUIPMENT OPERATORGROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPEN | $56.59 | $37.50 |
| ENGI0825-020 | POWER EQUIPMENT OPERATORGROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON | $60.13 | $37.50 |
| ENGI0825-020 | POWER EQUIPMENT OPERATORGROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, | $61.72 | $37.50 |
| ENGI0825-020 | POWER EQUIPMENT OPERATORGROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER W | $52.88 | $37.50 |
| ENGI0825-020 | POWER EQUIPMENT OPERATORGROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLID | $58.22 | $37.50 |
| ROOF0004-004 | ROOFERALL TYPES (SOMERSET COUNTY (NORTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE ALONG ROUTE #206 NORTH TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE)) | $44.52 | $32.25 |
| ROOF0030-029 | ROOFERSHINGLES (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT T | $35.95 | $21.85 |
| ROOF0030-029 | ROOFERSLATE AND TILE (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAI | $38.95 | $21.85 |
| ROOF0030-029 | ROOFERALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAI | $46.03 | $34.27 |
| SHEE0025-005 | SHEET METAL WORKERINCLUDING HVAC DUCT INSTALLATION | $51.30 | $51.55 |
| SFNJ0669-008 | SPRINKLER FITTERFIRE SPRINKLERS (SOMERSET COUNTY (TOWNSHIPS OF BRANCHBURG AND MONTGOMERY; BOROUGH OF ROCKY HILL)) | $49.97 | $41.35 |
| SFNJ0696-004 | SPRINKLER FITTERFIRE SPRINKLERS (SOMERSET COUNTY (REMAINDER OF COUNTY)) | $67.97 | $39.35 |
| BRNJ0007-001 | TILE FINISHER WORK GROUTING ALL EPOXY$10.00 ADDITIONAL PER DAY | $50.05 | $33.90 |
| BRNJ0007-001 | TILE SETTER | $64.90 | $37.28 |
| TEAM0469-005 | TRUCK DRIVERDUMP TRUCK HAZARDOUS WASTE REMOVAL WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE W | $48.63 | $42.66 |
| TEAM0469-005 | TRUCK DRIVEROFF THE ROAD TRUCK HAZARDOUS WASTE REMOVAL WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WAST | $48.78 | $42.66 |