Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Highway
Covers 1 county in New Hampshire: Strafford. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUNH2019-010 | CARPENTER(FORM WORK ONLY) | $24.04 | $2.60 |
| SUNH2019-010 | CARPENTER, EXCLUDES FORM WORK | $26.23 | $2.51 |
| SUNH2019-010 | CEMENT MASON/CONCRETE FINISHER | $21.78 | $0.00 |
| SUNH2019-010 | ELECTRICIAN | $29.00 | $2.78 |
| SUNH2019-010 | FENCE ERECTOR(CHAIN LINK FENCE) | $19.59 | $0.00 |
| SUNH2019-010 | HIGHWAY/PARKING LOT STRIPINGPAINTER | $20.87 | $0.00 |
| SUNH2019-010 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| INSTALLER - GUARDRAIL |
| $29.70 |
| $8.11 |
| SUNH2019-010 | IRONWORKER, REINFORCING | $22.21 | $8.19 |
| SUNH2019-010 | IRONWORKER, STRUCTURAL | $34.45 | $17.20 |
| SUNH2019-010 | LABORERASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $20.38 | $5.47 |
| SUNH2019-010 | LABORERCOMMON OR GENERAL | $18.79 | $2.60 |
| SUNH2019-010 | LABORERLANDSCAPE | $18.21 | $0.00 |
| SUNH2019-010 | LABORERPIPELAYER | $19.64 | $4.83 |
| SUNH2019-010 | OPERATORROLLER | $24.43 | $4.32 |
| SUNH2019-010 | OPERATORBOBCAT/SKID STEER/SKID LOADER | $25.01 | $9.93 |
| SUNH2019-010 | OPERATORAUGER | $26.07 | $0.00 |
| SUNH2019-010 | OPERATORBACKHOE/EXCAVATOR/TRACKHOE | $26.43 | $5.27 |
| SUNH2019-010 | OPERATORBROOM/SWEEPER | $25.08 | $4.60 |
| SUNH2019-010 | OPERATORBUCKET | $30.00 | $0.00 |
| SUNH2019-010 | OPERATORBULLDOZER | $25.97 | $6.59 |
| SUNH2019-010 | OPERATORCRANE | $29.76 | $3.29 |
| SUNH2019-010 | OPERATORGRADER/BLADE | $27.56 | $6.56 |
| SUNH2019-010 | OPERATORLOADER | $25.93 | $5.55 |
| SUNH2019-010 | OPERATORMECHANIC | $24.33 | $8.36 |
| SUNH2019-010 | OPERATORMILLING MACHINE | $28.55 | $6.88 |
| SUNH2019-010 | OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $27.93 | $5.10 |
| SUNH2019-010 | OPERATORPOUNDER | $36.21 | $9.46 |
| SUNH2019-010 | PAINTERSPRAY | $27.29 | $6.95 |
| SUNH2019-010 | TRAFFIC CONTROLFLAGGER | $12.05 | $1.37 |
| SUNH2019-010 | TRUCK DRIVERDUMP TRUCK | $21.41 | $4.05 |
| SUNH2019-010 | TRUCK DRIVERLOWBOY TRUCK | $22.75 | $4.95 |