Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in North Carolina: Iredell. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUNC2018-007 | BRICKLAYER | $19.00 | $0.00 |
| SUNC2018-007 | CARPENTER, EXCLUDES DRYWALL HANGING | $21.33 | $5.16 |
| SUNC2018-007 | CEMENT MASON/CONCRETE FINISHER | $18.79 | $0.00 |
| CARP0312-003 | DRYWALL HANGER | $29.00 | $11.20 |
| ELEC0379-001 | ELECTRICIAN | $32.31 | $13.66 |
| IRON0848-003 | IRONWORKER | $29.75 | $18.00 |
| SUNC2018-007 | LABORERPIPELAYER | $15.00 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $2.46 |
| SUNC2018-007 | LABORERCOMMON OR GENERAL | $13.97 | $7.82 |
| SUNC2018-007 | LABORERMASON TENDER - BRICK | $13.17 | $0.00 |
| SUNC2018-007 | LABORERMASON TENDER - CEMENT/CONCRETE | $13.00 | $4.54 |
| SUNC2018-007 | OPERATORBULLDOZER | $17.54 | $2.63 |
| SUNC2018-007 | OPERATORGRADER/BLADE | $22.68 | $3.27 |
| SUNC2018-007 | OPERATORROLLER | $15.31 | $1.46 |
| SUNC2018-007 | OPERATORBACKHOE/EXCAVATOR/TRACKHOE | $16.50 | $0.08 |
| SUNC2018-007 | OPERATORFORKLIFT | $16.75 | $0.00 |
| SUNC2018-007 | PAINTER | $15.55 | $1.05 |
| PLUM0421-006 | PIPEFITTER | $33.96 | $13.48 |
| SUNC2018-007 | PLUMBER | $22.96 | $4.81 |
| SUNC2018-007 | ROOFER | $18.26 | $4.38 |
| SHEE0005-008 | SHEET METAL WORKER(HVAC DUCT INSTALLATION ONLY) | $30.74 | $16.51 |
| SUNC2018-007 | SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $19.67 | $13.27 |
| SUNC2018-007 | SPRINKLER FITTER | $18.35 | $3.06 |
| SUNC2018-007 | TRUCK DRIVERDUMP TRUCK | $16.56 | $3.09 |