Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Montana: Golden Valley. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| BOIL0011-002 | BOILERMAKER | $38.75 | $32.31 |
| BRMT0010-001 | BRICKLAYER | $30.55 | $15.75 |
| SUMT2011-011 | CARPENTER(DRYWALL HANGING ONLY) | $22.69 | $0.00 |
| SUMT2011-011 | CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $20.58 | $5.88 |
| SUMT2011-011 | CEMENT MASON/CONCRETE FINISHER | $18.27 | $1.50 |
| ELEC0532-008 | ELECTRICIAN(Excluding Low Voltage Wiring for Alarms0 | $43.92 | $18.17 |
| SUMT2011-011 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| ELECTRICIAN(Low Voltage Wiring for Alarms) |
| $20.22 |
| $6.58 |
| SUMT2011-011 | FORM WORKER | $16.02 | $6.00 |
| ASBE0082-002 | HEAT AND FROST INSULATOR | $43.81 | $21.87 |
| IRON0732-013 | IRONWORKERREINFORCING AND STRUCTURAL | $36.83 | $25.30 |
| SUMT2011-011 | LABORERCOMMON OR GENERAL | $16.64 | $4.12 |
| SUMT2011-011 | LABORERMASON TENDER - BRICK | $18.37 | $5.94 |
| SUMT2011-011 | OPERATORFORKLIFT | $21.44 | $8.05 |
| SUMT2011-011 | OPERATOREXCAVATOR | $22.98 | $5.57 |
| SUMT2011-011 | PAINTERBRUSH, ROLLER AND SPRAY | $19.18 | $0.00 |
| PLUM0030-009 | PIPEFITTER, EXCLUDES HVAC PIPE INSTALLATION | $44.35 | $21.87 |
| SUMT2011-011 | PLUMBER(HVAC PIPE INSTALLATION) | $25.75 | $10.87 |
| SUMT2011-011 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $26.34 | $10.30 |
| ENGI0400-003 | POWER EQUIPMENT OPERATOR(4) CRANES 25-44 TONS ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $38.00 | $16.20 |
| ENGI0400-003 | POWER EQUIPMENT OPERATOR(5) CRANES 45-74 TONS ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $38.00 | $16.20 |
| ENGI0400-003 | POWER EQUIPMENT OPERATOR(6) CRANES 75 TO 144 TONS, WHIRLEY CRANES ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + | $40.00 | $16.20 |
| ENGI0400-003 | POWER EQUIPMENT OPERATOR(7) CRANES, 150 TONS TO INCLUDING 250 TONS (ADD $1.00 FOR EVERY 100 TONS OVER 250 TONS); CRANE, TOWER (ALL) ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 | $42.00 | $16.20 |
| ENGI0400-003 | POWER EQUIPMENT OPERATOR(1) A-FRAME TRUCK CRANE ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $21.51 | $16.20 |
| SUMT2011-011 | ROOFER | $15.44 | $1.81 |
| SHEE0103-009 | SHEET METAL WORKER(HVAC DUCT INSTALLATION ONLY) | $40.00 | $22.07 |
| SFMT0669-002 | SPRINKLER FITTER(FIRE SPRINKLERS) | $39.97 | $24.40 |
| SUMT2011-011 | TRUCK DRIVERDUMP TRUCK | $18.88 | $4.66 |