Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Missouri: Crawford. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| BOIL0027-001 | BOILERMAKER | $46.00 | $36.25 |
| BRMO0001-008 | BRICKLAYER | $41.15 | $23.90 |
| CARP0012-001 | CARPENTER(INCLUDING DRYWALL HANGING & FORM WORK) | $44.19 | $21.85 |
| CARP1310-001 | CARPENTER(FLOOR LAYING-CARPET AND VINYL ONLY) | $40.08 | $21.85 |
| PLAS0527-009 | CEMENT MASON/CONCRETE FINISHER | $36.63 | $9.85 |
| ELEC0257-002 | ELECTRICIAN(INCLUDING LOW VOLTAGE WIRING INSTALLER; ALARM, COMPUTER & TELEPHONE INSTALLATION) | $40.50 | $23.26 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| ELEV0003-001 | ELEVATOR MECHANIC. FOOTNOTESA) EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR LESS THAN 5 YEARS OF SERVICE B) EIGHT PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTM | $62.73 | $38.44 |
| PAIN0513-001 | GLAZIER | $40.00 | $24.25 |
| IRON0396-007 | IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL | $41.67 | $31.25 |
| LABO0840-006 | LABORERBRICK & CEMENT/CONCRETE MASON TENDER | $32.23 | $15.30 |
| LABO0840-006 | LABORERCOMMON OR GENERAL; ASPHALT SHOVELER; PIPELAYER | $30.33 | $15.30 |
| SUMO2023-001 | OPERATORHOIST | $26.02 | $13.01 |
| PAIN1185-009 | PAINTER(DRYWALL FINISHING/TAPING) | $34.90 | $17.21 |
| PAIN1185-009 | PAINTER(BRUSH AND ROLLER) | $33.90 | $17.21 |
| SUMO2023-001 | PAINTERSPRAY | $17.78 | $0.00 |
| PLUM0562-008 | PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION(MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER) | $48.66 | $22.79 |
| PLUM0562-008 | PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION(MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION) | $50.60 | $30.13 |
| PLUM0562-008 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION(MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION) | $50.60 | $30.13 |
| PLUM0562-008 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION(MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER) | $48.66 | $22.79 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSGRADER/BLADE | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSFORKLIFT | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSBOBCAT/SKID LOADER | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSBACKHOE/EXCAVATOR | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSPAVER | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSLOADER | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSCRANE | $39.06 | $30.38 |
| ENGI0513-005 | POWER EQUIPMENT OPERATORSROLLER | $39.06 | $30.38 |
| ROOF0002-001 | ROOFER | $40.00 | $22.05 |
| SHEE0036-001 | SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $52.00 | $27.12 |
| SFMO0669-004 | SPRINKLER FITTER(FIRE SPRINKLERS) | $45.94 | $27.52 |
| BRMO0018-007 | TILE FINISHER | $28.50 | $18.15 |
| BRMO0018-007 | TILE SETTER | $34.09 | $19.91 |