Pulling the wage determination…
Revision 2 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Missouri: Chariton. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 2). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0027-004 | ASBESTOS WORKER/HEAT & FROST INSULATOR | $45.60 | $35.47 |
| BRMO0011-001 | BRICKLAYER | $32.79 | $21.31 |
| CARP0010-005 | CARPENTER, EXCLUDES FORM WORK | $31.51 | $22.25 |
| SUMO2010-008 | CEMENT MASON/CONCRETE FINISHER | $18.86 | $7.50 |
| ELEC0257-011 | ELECTRICIAN | $40.50 | $23.26 |
| SUMO2010-008 | FORM WORKER | $26.44 | $0.00 |
| SUMO2010-008 | GLAZIER | $14.19 | $5.19 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| IRON0010-004 | IRONWORKERREINFORCING AND STRUCTURAL | $36.00 | $34.25 |
| LABO0955-002 | LABORER(BRICK MASON TENDER) | $29.71 | $15.50 |
| LABO0955-002 | LABORER(LANDSCAPE) | $27.71 | $15.50 |
| SUMO2010-008 | LABORERCOMMON OR GENERAL | $23.20 | $0.00 |
| SUMO2010-008 | OPERATORBACKHOE/TRACKHOE | $31.12 | $0.00 |
| PAIN1185-002 | PAINTER(BRUSH & ROLLER ONLY) | $28.56 | $17.21 |
| SUMO2010-008 | PAINTERSPRAY | $18.79 | $8.12 |
| PLUM0562-011 | PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION(ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | $52.60 | $29.93 |
| PLUM0562-011 | PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION(ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | $50.66 | $23.34 |
| PLUM0562-011 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION(ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | $52.60 | $29.93 |
| PLUM0562-011 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION(ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | $50.66 | $23.34 |
| ENGI0101-021 | POWER EQUIPMENT OPERATOR(PAVER) | $45.48 | $22.42 |
| ENGI0101-021 | POWER EQUIPMENT OPERATORROLLER | $45.48 | $22.42 |
| ENGI0101-021 | POWER EQUIPMENT OPERATOR(LOADER) | $45.48 | $22.42 |
| ENGI0101-021 | POWER EQUIPMENT OPERATORGRADER/BLADE | $45.48 | $22.42 |
| ROOF0020-001 | ROOFER | $38.45 | $22.29 |
| SHEE0002-017 | SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $47.20 | $26.28 |
| BRMO0011-001 | TILE SETTER | $32.79 | $21.31 |
| SUMO2010-008 | TRUCK DRIVERDUMP TRUCK | $28.92 | $0.00 |