Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Heavy
Covers 83 counties in Michigan: Alcona, Alger, Allegan, Alpena, Antrim, Arenac, Baraga, Barry, Bay, Benzie, Berrien, Branch and 71 more. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, ALGER, BARAGA, CHIPPEWA, DELTA, DICKINSON, GOGEBIC, HOUGHTON, IRON, KEWEENAW, LUCE, MACKINAC, MARQUETTE, MENOMINEE, ONTONAGON AND SCHOOLCRAFT COUNTIES - ZONE 11 (LEVELS A, B OR C) | $25.18 | $12.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, IONIA COUNTY (EXCEPT THE CITY OF PORTLAND); KALAMAZOO, KENT, LAKE, MANISTEE, MASON, MECOSTA, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA, OTTAWA, ST. JOSEPH AND VAN BUREN COUNTIES - ZONE 9 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $20.80 | $12.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, ALLEGAN, BARRY, BERRIEN, BRANCH, CALHOUN, CASS, IONIA COUNTY (EXCEPT THE CITY OF PORTLAND); KALAMAZOO, KENT, LAKE, MANISTEE, MASON, MECOSTA, MONTCALM, MUSKEGON, NEWAYGO, OCEANA, OSCEOLA, OTTAWA, ST. JOSEPH AND VAN BUREN COUNTIES - ZONE 9 (LEVELS A, B OR C) | $21.88 | $13.26 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $23.74 |
| $12.95 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENTclass a | $17.64 | $12.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENTclass b | $18.64 | $12.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, CLINTON, EATON AND INGHAM COUNTIES; IONIA COUNTY (CITY OF PORTLAND); LIVINGSTON COUNTY (WEST OF OAK GROVE RD., INCLUDING THE CITY OF HOWELL) - ZONE 6 (LEVELS A, B OR C) | $26.33 | $12.95 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, GENESEE, LAPEER AND SHIAWASSEE COUNTIES - ZONE 7 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $23.20 | $13.80 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, GENESEE, LAPEER AND SHIAWASSEE COUNTIES - ZONE 7 (LEVELS A, B OR C) | $24.20 | $13.80 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, HILLSDALE, JACKSON AND LENAWEE COUNTIES - ZONE 4 (LEVELS A, B OR C) | $27.13 | $14.95 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, LIVINGSTON COUNTY (EAST OF OAK GROVE RD. AND SOUTH OF M-59, EXCLUDING THE CITY OF HOWELL); AND WASHTENAW COUNTY - ZONE 3 (LEVELS A, B OR C) | $29.93 | $14.20 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, LIVINGSTON COUNTY (EAST OF OAK GROVE RD. AND SOUTH OF M-59, EXCLUDING THE CITY OF HOWELL); AND WASHTENAW COUNTY - ZONE 3 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $28.93 | $14.20 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, MACOMB AND WAYNE COUNTIES - ZONE 1 (LEVELS A, B OR C) | $29.93 | $16.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, MACOMB AND WAYNE COUNTIES - ZONE 1 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $28.93 | $16.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, MONROE COUNTY - ZONE 4 (LEVELS A, B OR C) | $31.75 | $14.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, MONROE COUNTY - ZONE 4 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $31.75 | $14.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, OAKLAND COUNTY AND THE NORTHEAST PORTION OF LIVINGSTON COUNTY BORDERED BY OAK GROVE ROAD ON THE WEST AND M-59 ON THE SOUTH - ZONE 2 (LEVEL A, B, C) | $29.93 | $16.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, OAKLAND COUNTY AND THE NORTHEAST PORTION OF LIVINGSTON COUNTY BORDERED BY OAK GROVE ROAD ON THE WEST AND M-59 ON THE SOUTH - ZONE 2 WORK PERFORMED IN CONJUNCTION WITH SITE PREPARATION NOT REQUIRING THE USE OF PERSONAL PROTECTIVE EQUIPMENT; ALSO, LEVEL D | $28.93 | $16.90 |
| LABO0005-006 | LABORERS - HAZARDOUS WASTE ABATEMENT, SANILAC AND ST. CLAIR COUNTIES - ZONE 5 (LEVELS A, B OR C) | $26.21 | $16.62 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $29.88 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL B AND C) | $32.23 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D) | $31.02 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL A) | $33.27 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL B AND C) | $31.91 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL A) | $32.97 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL D) | $30.72 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $30.47 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $30.77 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL A) | $30.32 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL B AND C) | $29.37 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL D) | $28.07 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $27.82 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL A) | $25.92 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL B AND C) | $24.98 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL D) | $23.68 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $23.43 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL B AND C) | $34.03 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D) | $29.04 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL A) | $31.29 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $28.79 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL B AND C) | $30.34 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL A) | $34.68 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D) | $32.43 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL B AND C) | $33.73 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $32.18 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $32.48 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL A) | $34.98 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D) | $32.73 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL A) | $32.03 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL B AND C) | $31.08 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL D) | $29.78 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $29.53 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL A) | $27.80 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL B AND C) | $26.85 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL D) | $25.55 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $25.30 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, PWER SHOVEL OPERATOR | $32.05 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D) | $30.75 | $19.70 |
| ENGI0325-011 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL A) | $33.00 | $19.70 |