Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Michigan: Sanilac. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUMI2011-074 | ASBESTOS WORKER/HEAT & FROST INSULATOR | $19.82 | $7.31 |
| BOIL0169-002 | BOILERMAKER | $43.50 | $37.64 |
| BRMI0001-005 | BRICKLAYER | $38.87 | $25.18 |
| CARP0687-010 | CARPENTER(ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION) | $42.44 | $31.43 |
| SUMI2011-074 | CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYING-CARPET | $15.38 | $2.31 |
| SUMI2011-074 | CEMENT MASON/CONCRETE FINISHER | $19.33 | $6.80 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| ELEC0058-005 | ELECTRICIAN(EXCLUDES LOW VOLTAGE WIRING) | $51.32 | $28.44 |
| ELEC0058-005 | ELECTRICIAN, LOW VOLTAGE WIRING ONLY(INSTALLER) | $30.12 | $14.57 |
| ELEC0058-005 | ELECTRICIAN, LOW VOLTAGE WIRING ONLY(TECHNICIAN) | $37.62 | $14.80 |
| SUMI2011-074 | FLOOR LAYERCARPET | $19.59 | $7.57 |
| SUMI2011-074 | GLAZIER | $16.95 | $4.74 |
| IRON0025-009 | IRONWORKERSTRUCTURAL (METAL BUILDING ERECTION ONLY) | $30.02 | $27.43 |
| IRON0025-010 | IRONWORKER, REINFORCING | $36.55 | $33.37 |
| IRON0025-010 | IRONWORKER, STRUCTURAL | $36.55 | $35.93 |
| LABO1075-013 | LABORERCOMMON OR GENERAL; MASON TENDER - BRICK; PIPELAYER; AND SANDBLASTER EXCLUDES OPEN CUT CONSTRUCTION | $31.30 | $18.40 |
| SUMI2011-074 | LABORERMASON TENDER - CEMENT/CONCRETE | $16.11 | $4.51 |
| SUMI2011-074 | LABORERLANDSCAPE & IRRIGATION | $12.84 | $0.00 |
| CARP1102-003 | MILLWRIGHT | $42.92 | $39.13 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER; TOWER CRANE; GANTRY CRANE AND WHIRLEY DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $38.18 | $24.85 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 3 CRANE; LOADER; PAVER; SCRAPER; STIFF LEG DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $40.83 | $24.85 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $36.47 | $24.85 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $30.61 | $24.85 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 6 OILER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $26.13 | $24.85 |
| ENGI0324-023 | OPERATORPOWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $44.13 | $24.85 |
| SUMI2011-074 | OPERATORGRADER/BLADE | $24.04 | $6.03 |
| SUMI2011-074 | OPERATORROLLER | $28.02 | $7.07 |
| SUMI2011-074 | OPERATORTRACTOR | $19.60 | $7.31 |
| SUMI2011-074 | OPERATORBACKHOE/EXCAVATOR | $20.34 | $14.59 |
| SUMI2011-074 | OPERATORBULLDOZER | $22.34 | $1.22 |
| PAIN1474-007 | PAINTERDRYWALL FINISHING/TAPING | $23.79 | $12.02 |
| PAIN1474-007 | PAINTERBRUSH, ROLLER AND SPRAY | $23.79 | $12.02 |
| PLUM0636-011 | PIPEFITTER(INCLUDES HVAC PIPE INSTALLATION; EXCLUDES HVAC SYSTEM INSTALLATION) | $40.30 | $38.80 |
| PLAS0067-005 | PLASTERER | $30.63 | $14.07 |
| SUMI2011-074 | PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | $16.13 | $3.67 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $40.83 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL A) | $28.86 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL B AND C) | $26.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL A) | $28.86 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D) | $42.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL B AND C) | $40.83 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $36.47 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $44.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL A) | $42.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D) | $34.72 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL A) | $40.83 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL B AND C) | $44.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL D) | $38.18 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 1 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $28.86 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL A) | $36.43 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL B AND C) | $36.47 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL D) | $39.08 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: GROUP 2 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $30.61 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D) | $26.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL A) | $30.61 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D WHEN CAPPING LANDFILL) | $26.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL B AND C) | $36.47 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D) | $34.72 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL A) | $34.72 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL B AND C) | $26.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL A) | $42.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL A) | $39.08 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL B AND C) | $30.61 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL D) | $26.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL A) | $26.38 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL B AND C) | $44.13 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL D) | $39.08 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 2 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $36.43 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL B AND C) | $36.43 | $24.85 |
| ENGI0324-023 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D) | $38.18 | $24.85 |
| SUMI2011-074 | ROOFER | $15.73 | $7.41 |
| SHEE0080-007 | SHEET METAL WORKER(EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | $42.51 | $35.77 |
| SHEE0080-007 | SHEET METAL WORKER(HVAC DUCT & SYSTEM INSTALLATION) | $42.51 | $35.77 |
| SFMI0669-003 | SPRINKLER FITTER(FIRE SPRINKLERS) | $41.34 | $27.39 |
| BRMI0001-005 | TILE SETTER | $37.88 | $22.67 |
| SUMI2011-074 | TRUCK DRIVERFLATBED TRUCK | $16.80 | $3.97 |
| SUMI2011-074 | TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.65 | $3.12 |