Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Michigan: Midland. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUMI2011-063 | ASBESTOS WORKER/HEAT & FROST INSULATOR | $16.19 | $4.53 |
| BOIL0169-002 | BOILERMAKER | $43.50 | $37.64 |
| SUMI2011-063 | BRICKLAYER | $21.43 | $5.72 |
| CARP0706-022 | CARPENTER(ACOUSTICAL CEILING INSTALLATION AND METAL STUD INSTALLATION) | $35.86 | $23.69 |
| SUMI2011-063 | CARPENTER(FORM WORK ONLY) | $20.00 | $1.22 |
| SUMI2011-063 | CARPENTER(DRYWALL HANGING ONLY) | $18.98 | $0.00 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| SUMI2011-063 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION |
| $20.38 |
| $4.88 |
| PLAS0016-039 | CEMENT MASON/CONCRETE FINISHER | $25.47 | $12.38 |
| ELEC0557-005 | ELECTRICIANEXCLUDES LOW VOLTAGE WIRING (TOWNSHIPS OF INGERSOLL, JASPER, MT. HALEY AND PORTER) | $39.50 | $25.03 |
| ELEC0692-023 | ELECTRICIANEXCLUDES LOW VOLTAGE WIRING (ALL TOWNSHIPS EXCEPT INGERSOLL, JASPER, MT. HALEY, & PORTER) | $40.00 | $26.52 |
| SUMI2011-063 | FLOOR LAYERCARPET | $19.27 | $7.57 |
| SUMI2011-063 | GLAZIER | $16.95 | $4.74 |
| IRON0025-003 | IRONWORKERREINFORCING | $36.55 | $33.37 |
| IRON0025-003 | IRONWORKERSTRUCTURAL (METAL BUILDING ERECTION ONLY) | $30.02 | $27.43 |
| SUMI2011-063 | IRONWORKER, STRUCTURAL | $19.75 | $11.54 |
| LABO1098-032 | LABORER(COMMON OR GENERAL; MASON TENDER - CEMENT/CONCRETE; AND PIPELAYER) | $27.68 | $13.45 |
| LABO1098-032 | LABORERSANDBLASTER | $28.21 | $13.45 |
| SUMI2011-063 | LABORERLANDSCAPE & IRRIGATION | $12.84 | $0.00 |
| SUMI2011-063 | LABORERMASON TENDER - BRICK | $14.25 | $3.89 |
| CARP1102-003 | MILLWRIGHT | $42.92 | $39.13 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 6 OILER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR; CRANE; LOADER; PAVER; SCRAPER; STIFF LEG DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 |
| ENGI0324-022 | OPERATORPOWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 |
| SUMI2011-063 | OPERATORROLLER | $28.02 | $7.07 |
| SUMI2011-063 | OPERATORBULLDOZER | $22.34 | $1.22 |
| SUMI2011-063 | OPERATORGRADER/BLADE | $24.04 | $6.03 |
| SUMI2011-063 | OPERATORTRACTOR | $19.60 | $7.31 |
| PAIN1803-001 | PAINTERDRYWALL FINISHING/TAPING | $30.22 | $22.22 |
| PAIN1803-001 | PAINTERBRUSH, ROLLER AND SPRAY | $29.23 | $19.11 |
| PLUM0085-004 | PIPEFITTER(HVAC PIPE INSTALLATION ONLY) | $45.50 | $21.75 |
| PLUM0085-004 | PIPEFITTER(EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) | $45.50 | $21.75 |
| PLAS0016-039 | PLASTERER | $26.32 | $12.88 |
| PLUM0085-004 | PLUMBER(EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) | $43.50 | $22.10 |
| SUMI2011-063 | ROOFER | $15.73 | $7.41 |
| SHEE0007-020 | SHEET METAL WORKER(HVAC DUCT & SYSTEM INSTALLATION) | $26.83 | $23.78 |
| SUMI2011-063 | SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | $17.57 | $11.51 |
| SFMI0669-003 | SPRINKLER FITTER(FIRE SPRINKLERS) | $41.34 | $27.39 |
| BRMI0009-021 | TILE SETTER | $31.43 | $21.13 |
| SUMI2011-063 | TRUCK DRIVERFLATBED TRUCK | $14.40 | $2.31 |
| SUMI2011-063 | TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.65 | $3.12 |