Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Michigan: Lenawee. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0045-003 | ASBESTOS WORKER/HEAT & FROST INSULATOR(TOWNSHIPS OF BLISSFIELD, CLINTON, DEERFIELD, FAIRFIELD, MACON, OGDEN, PALMYRA, RAISIN, RIDGEWAY, RIGA, & TECUMSEH) | $36.00 | $20.15 |
| ASBE0047-007 | ASBESTOS WORKER/HEAT & FROST INSULATOR(TOWNSHIPS OF ADRIAN, CAMBRIDGE, DOVER, FRANKLIN, HUDSON, MADISON, MADINA, ROLLIN, ROME, SENECA, & WOODSTOCK) | $36.62 | $19.78 |
| BOIL0085-004 | BOILERMAKER | $43.50 | $37.64 |
| BRMI0009-005 | BRICKLAYER FOOTNOTEPAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $35.83 | $22.18 |
| CARP1004-021 | CARPENTER(INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION) |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $35.41 |
| $21.06 |
| PLAS0886-007 | CEMENT MASON/CONCRETE FINISHER | $27.18 | $18.11 |
| ELEC0008-004 | ELECTRICIAN(EXCLUDES LOW VOLTAGE WIRING) | $48.40 | $17.79 |
| SUMI2011-056 | FLOOR LAYERCARPET | $19.59 | $7.57 |
| SUMI2011-056 | GLAZIER | $16.95 | $4.74 |
| IRON0055-004 | IRONWORKERREINFORCING & STRUCTURAL | $35.50 | $29.20 |
| LABO0499-007 | LABORER(COMMON OR GENERAL; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; PIPELAYER; AND SANDBLASTER) | $32.35 | $13.45 |
| SUMI2011-056 | LABORERLANDSCAPE & IRRIGATION | $12.84 | $0.00 |
| CARP1102-003 | MILLWRIGHT | $42.92 | $39.13 |
| SUMI2011-056 | OPERATORGRADER/BLADE | $24.04 | $6.03 |
| SUMI2011-056 | OPERATORBULLDOZER | $22.34 | $1.22 |
| SUMI2011-056 | OPERATORTRACTOR | $19.60 | $7.31 |
| SUMI2011-056 | OPERATORROLLER | $28.02 | $7.07 |
| SUMI2011-056 | OPERATORBACKHOE/EXCAVATOR | $29.04 | $9.76 |
| PAIN0022-003 | PAINTERBRUSH AND ROLLER | $32.85 | $20.41 |
| PAIN0022-003 | PAINTERDRYWALL FINISHING/TAPING | $32.85 | $20.41 |
| PAIN0022-003 | PAINTERSPRAY | $26.86 | $17.66 |
| PLUM0190-002 | PIPEFITTERHVAC PIPE INSTALLATION ONLY (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $42.26 | $23.70 |
| PLUM0190-002 | PIPEFITTEREXCLUDES HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $51.30 | $25.87 |
| PLUM0333-009 | PIPEFITTEREXCLUDING HVAC PIPE & SYSTEM INSTALLATION (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $46.29 | $25.43 |
| PLUM0333-009 | PIPEFITTERHVAC PIPE INSTALLATION ONLY (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $46.29 | $25.43 |
| PLAS0886-007 | PLASTERER | $27.41 | $16.10 |
| PLUM0190-002 | PLUMBEREXCLUDING HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $49.43 | $24.36 |
| PLUM0333-009 | PLUMBEREXCLUDING HVAC PIPE & SYSTEM INSTALLATION (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH) | $46.29 | $25.43 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 3 CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $48.29 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 4 CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $47.99 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 5 CRANE WITH BOOM AND JIB OR LEADS 120' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $47.17 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 6 REGULAR CRANE OPERATOR FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $46.31 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 7 BOBCAT/SKID LOADER; LOADER;PAVER; SCRAPER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $45.34 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 8 FORKLIFT & EXTEND-A-BOOM FORKLIFT FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $43.63 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 9 OILER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $35.29 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 2 CRANE WITH BOOM AND JIB OR LEADS 300' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $49.79 | $25.35 |
| ENGI0324-019 | POWER EQUIPMENT OPERATORGROUP 1 CRANE WITH BOOM AND JIB OR LEADS 400' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE | $51.29 | $25.35 |
| SUMI2011-056 | ROOFER | $15.73 | $7.41 |
| SHEE0033-033 | SHEET METAL WORKER(HVAC DUCT & SYSTEM INSTALLATION) | $30.80 | $21.51 |
| SHEE0033-033 | SHEET METAL WORKER(EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | $30.80 | $21.51 |
| SFMI0669-003 | SPRINKLER FITTER(FIRE SPRINKLERS) | $41.34 | $27.39 |
| BRMI0009-005 | TILE SETTER FOOTNOTEPAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $35.83 | $22.18 |
| SUMI2011-056 | TRUCK DRIVERFLATBED TRUCK | $16.80 | $3.97 |
| SUMI2011-056 | TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.50 | $0.00 |