Pulling the wage determination…
Revision 2 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Michigan: Genesee. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 2). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| ASBE0047-002 | ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 |
| BOIL0169-001 | BOILERMAKER | $43.50 | $36.74 |
| BRMI0009-014 | BRICKLAYER FOOTNOTEPAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $38.00 | $26.49 |
| CARP0706-001 | CARPENTER, INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | $36.46 | $23.69 |
| PLAS0016-005 | CEMENT MASON/CONCRETE FINISHER | $25.58 | $12.88 |
| PAIN1052-004 | DRYWALL FINISHER/TAPER(DRYWALL SANDING) |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $33.54 |
| $18.12 |
| ELEC0948-001 | ELECTRICIAN(EXCLUDES LOW VOLTAGE WIRING) | $44.83 | $26.96 |
| IRON0025-019 | IRONWORKERSTRUCTURAL | $36.55 | $35.93 |
| IRON0025-019 | IRONWORKERREINFORCING | $36.55 | $33.37 |
| SUMI2011-008 | IRONWORKER, ORNAMENTAL | $18.48 | $7.93 |
| LABO0334-005 | LABORERLANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 |
| LABO0334-005 | LABORERLANDSCAPE & IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 |
| LABO1075-002 | LABORERCOMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE, PIPELAYER; SANDBLASTER | $29.46 | $16.10 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR/TRACKHOE; BULLDOZER; CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; LOADER; ROLLER; SCRAPER; STIFF LEG DERRICK; TRACTOR; TRENCHER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 |
| ENGI0324-011 | OPERATORPOWER EQUIPMENT: GROUP 5 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 |
| PAIN1052-001 | PAINTERSPRAY | $31.01 | $17.29 |
| PAIN1052-001 | PAINTERBRUSH & ROLER | $32.58 | $18.12 |
| PLUM0370-002 | PIPEFITTER(INCLUDES HVAC PIPE INSTALLATION; EXCLUDES HVAC SYSTEM INSTALLATION) | $46.61 | $22.95 |
| PLUM0370-002 | PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $46.61 | $22.95 |
| PAIN1052-001 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $31.01 | $17.19 |
| PAIN1052-001 | POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL D) | $31.01 | $17.29 |
| ROOF0149-005 | ROOFER | $30.38 | $19.97 |
| SHEE0007-008 | SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $35.19 | $23.57 |
| SFMI0669-001 | SPRINKLER FITTER(FIRE SPRINKLERS) | $41.34 | $27.39 |
| BRMI0009-014 | TILE FINISHER FOOTNOTEPAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $28.21 | $20.88 |
| BRMI0009-014 | TILE SETTER FOOTNOTEPAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.31 | $23.20 |
| SUMI2011-008 | TRUCK DRIVERTRACTOR HAUL TRUCK | $13.57 | $1.18 |