Pulling the wage determination…
Revision 2 · modified May 18, 2026 · published May 18, 2026 · Heavy
Covers 1 county in Michigan: Muskegon. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 2). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| CARP0100-009 | CARPENTER, INCLUDES FORM WORK | $31.50 | $21.15 |
| PLAS0016-017 | CEMENT MASON/CONCRETE FINISHER | $21.15 | $12.78 |
| TEAM0007-010 | DAILY | $33.55 | $0.75 |
| ELEC0275-001 | ELECTRICIAN | $36.52 | $25.15 |
| IRON0025-011 | IRONWORKERSTRUCTURAL | $36.55 | $34.04 |
| IRON0025-011 | IRONWORKERREINFORCING | $36.55 | $34.04 |
| LABO0334-006 | LABORER |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $22.55 |
| $12.95 |
| LABO0334-006 | LABORER((1) COMMON OR GENERAL) | $22.42 | $12.95 |
| LABO0334-006 | LABORER((4) GRADE CHECKER) | $22.73 | $12.95 |
| LABO0355-019 | LABORER(COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE) (EXCLUDES OPEN CUT CONSTRUCTION) | $24.55 | $13.45 |
| SUMI2010-065 | LABORERPIPELAYER | $15.54 | $4.16 |
| SUMI2010-065 | LABORERLANDSCAPE | $12.21 | $1.96 |
| ENGI0326-009 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 BORING MACHINE; ROLLER; SCRAPER; TRACTOR; TRENCHER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | $44.00 | $25.25 |
| ENGI0326-009 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BOOM TRUCK (NON-SWINGING) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | $41.32 | $25.25 |
| ENGI0326-009 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | $41.32 | $25.25 |
| ENGI0326-009 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. SWING BOOM TRUCK OPERATOR OVER 12 TONS-$.50 PER HOUR | $35.46 | $25.25 |
| SUMI2010-065 | OPERATORBACKHOE/EXCAVATOR | $20.94 | $8.15 |
| SUMI2010-065 | OPERATORLOADER | $17.52 | $5.51 |
| SUMI2010-065 | OPERATORGRADER/BLADE | $16.64 | $0.00 |
| SUMI2010-065 | OPERATORCRANE | $18.50 | $5.10 |
| SUMI2010-065 | OPERATORBULLDOZER | $20.48 | $6.14 |
| PAIN0845-017 | PAINTERBRUSH, ROLLER AND SPRAY | $21.89 | $11.85 |
| PLUM0174-003 | PLUMBER | $39.80 | $23.82 |
| ENGI0325-016 | POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION(INCLUDING SEWER): GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 |
| ENGI0325-016 | POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION(INCLUDING SEWER): GROUP 1 BORING MACHINE, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 |
| ENGI0325-016 | POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION(INCLUDING SEWER): GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 |
| ENGI0325-016 | POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION(INCLUDING SEWER): GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 |
| SUMI2010-065 | TRUCK DRIVERDUMP TRUCK | $17.00 | $5.71 |
| SUMI2010-065 | TRUCK DRIVEROFF THE ROAD TRUCK | $20.82 | $3.69 |
| SUMI2010-065 | TRUCK DRIVERTRACTOR HAUL TRUCK | $16.50 | $4.89 |
| TEAM0007-010 | TRUCK DRIVERLOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A | $470.70 | PER WEEK. B. $68.70 |