Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Heavy
Covers 1 county in Michigan: Ingham. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| CARP1004-017 | CARPENTER, INCLUDES FORM WORK | $36.21 | $21.06 |
| PLAS0016-027 | CEMENT MASON/CONCRETE FINISHER | $24.64 | $12.88 |
| TEAM0007-011 | DAILY | $33.55 | $0.75 |
| ELEC0252-007 | ELECTRICIAN(TOWNSHIPS OF BUNKER HILL, LESLIE, ONONDAGA & STOCKBRIDGE) | $56.05 | $30.52 |
| ELEC0665-015 | ELECTRICIAN(TOWNSHIPS OF ALAIEDON, AURELIUS, DELHI, INGHAM, LANSING, LEROY, LOCKE, MERIDIAN, VEVAY, WHEATFIELD, WHITE OAK AND WILLIAMSON) | $45.00 | $31.37 |
| IRON0025-006 | IRONWORKERSTRUCTURAL | $36.55 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $35.93 |
| IRON0025-006 | IRONWORKERREINFORCING | $36.55 | $33.37 |
| LABO0334-013 | LABORER((1) COMMON OR GENERAL) | $23.39 | $13.15 |
| LABO0334-013 | LABORER((2) MASON TENDER-CEMENT/CONCRETE) | $23.53 | $13.15 |
| LABO0334-013 | LABORER((4) GRADE CHECKER) | $23.70 | $13.15 |
| LABO0334-013 | LABORER((5) PIPELAYER) | $23.84 | $13.15 |
| LABO0499-024 | LABORERCOMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER (EXCLUDES OPEN CUT CONSTRUCTION) | $32.53 | $13.45 |
| SUMI2010-056 | LABORERLANDSCAPE | $12.25 | $0.00 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.32 | $25.25 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $35.46 | $25.25 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.32 | $25.25 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLER; SCRAPER; TRACTOR; TRENCHER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $44.00 | $25.25 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $48.98 | $25.25 |
| ENGI0326-011 | OPERATORPOWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $45.68 | $25.25 |
| PAIN0845-017 | PAINTERBRUSH, ROLLER AND SPRAY | $21.89 | $11.85 |
| PLUM0333-020 | PLUMBER/PIPEFITTER | $42.29 | $23.94 |
| ENGI0325-009 | POWER EQUIPMENT OPERATORUNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 |
| ENGI0325-009 | POWER EQUIPMENT OPERATORUNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 |
| ENGI0325-009 | POWER EQUIPMENT OPERATORUNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 |
| ENGI0325-009 | POWER EQUIPMENT OPERATORUNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 |
| SUMI2010-056 | TRUCK DRIVEROFF THE ROAD TRUCK | $20.82 | $3.69 |
| SUMI2010-056 | TRUCK DRIVERDUMP TRUCK | $18.00 | $6.43 |
| TEAM0007-011 | TRUCK DRIVERLOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A | $470.70 | PER WEEK. B. $68.70 |
| TEAM0007-011 | TRUCK DRIVERTRACTOR HAUL TRUCK FOOTNOTE: A | $470.70 | PER WEEK. B. $68.70 DAILY.................$ 33.30 0.75 |