Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Highway
Covers 1 county in Massachusetts: Barnstable. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUMA2014-005 | CARPENTER, INCLUDES FORM WORK | $43.64 | $22.09 |
| SUMA2014-005 | CEMENT MASON/CONCRETE FINISHER | $56.70 | $21.08 |
| ELEC0223-001 | ELECTRICIAN(INCLUDES TRAFFIC SIGNALIZATION) | $50.02 | $31.05 |
| IRON0007-026 | IRONWORKERORNAMENTAL AND STRUCTURAL | $57.87 | $37.67 |
| SUMA2014-005 | IRONWORKER, REINFORCING | $44.52 | $19.36 |
| LABO0133-001 | LABORERCONCRETE SURFACER | $46.20 | $29.85 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| LABO0385-001 |
| LABORERFENCE ERECTION |
| $38.95 |
| $29.41 |
| LABO0385-001 | LABORERCOMMON OR GENERAL | $38.95 | $29.41 |
| LABO0596-009 | LABORER(GUARDRAIL INSTALLATION) | $35.00 | $26.91 |
| SUMA2014-005 | LABORERJACK HAMMER | $38.69 | $17.33 |
| SUMA2014-005 | LABORERASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $33.65 | $17.32 |
| SUMA2014-005 | LABORERCONCRETE SAW (HAND HELD/WALK BEHIND) | $44.43 | $14.18 |
| LABO0385-005 | LABORER LANDSCAPE | $38.95 | $29.41 |
| SUMA2014-005 | OPERATORPILEDRIVER | $42.56 | $17.34 |
| SUMA2014-005 | OPERATORFORKLIFT | $64.67 | $0.00 |
| SUMA2014-005 | OPERATORMECHANIC | $48.74 | $11.79 |
| PAIN0035-023 | PAINTERSTEEL | $56.76 | $36.00 |
| SUMA2014-005 | PAINTERSPRAY (LINESTRIPING) | $47.30 | $6.42 |
| ENGI0004-032 | POWER EQUIPMENT OPERATORGROUP 1 BACKHOE/EXCAVATOR/TRACKHOE; BOBCAT/SKID STEER/SKID LOADER; BROOM/SWEEPER; CRANE; GRADALL; LOADER; PAVER (ASPHALT, AGGREGATE, AND CONCRETE); POST DRIVER (GUARDRAIL/FENCES) FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, LABOR DAY, MEMORIAL DAY, INDEPENDENCE DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, CHRISTMAS DAY | $57.83 | $33.70 |
| ENGI0004-032 | POWER EQUIPMENT OPERATOR GROUP 2 BULLDOZER; GRADER/BLADE; MILLING MACHINE; ROLLER FOOTNOTE FOR POWER EQUIPMENT OPERATORSA. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, LABOR DAY, MEMORIAL DAY, INDEPENDENCE DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, CHRISTMAS DAY | $57.18 | $33.70 |
| SUMA2014-005 | TRAFFIC CONTROLFLAGGER | $23.00 | $20.44 |
| SUMA2014-005 | TRAFFIC CONTROLLABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $53.35 | $12.78 |
| SUMA2014-005 | TRUCK DRIVERCONCRETE TRUCK | $33.69 | $15.79 |
| SUMA2014-005 | TRUCK DRIVERFLATBED TRUCK | $48.53 | $0.00 |
| TEAM0059-001 | TRUCK DRIVERDUMP TRUCK FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.78 | $37.35 |