Pulling the wage determination…
Revision 1 · modified May 18, 2026 · published May 18, 2026 · Highway
Covers 1 county in Kansas: Johnson. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| CARP0315-006 | CARPENTER | $43.28 | $21.25 |
| PLAS0518-004 | CEMENT MASON/CONCRETE FINISHER | $39.06 | $18.71 |
| SUKS2019-079 | ELECTRICIAN | $29.93 | $14.14 |
| IRON0010-015 | IRONWORKER(REINFORCING AND STRUCTURAL) | $39.00 | $34.25 |
| LABO0663-017 | LABORERCONCRETE SAW (HAND HELD/WALK BEHIND) | $37.45 | $15.87 |
| LABO1290-002 | LABORERASPHALT, INCLUDES RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR | $37.45 | $15.87 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| SUKS2019-079 |
| LABORERCOMMON OR GENERAL |
| $27.81 |
| $14.30 |
| SUKS2019-079 | LABORERMASON TENDER - CEMENT/CONCRETE | $29.75 | $12.83 |
| SUKS2019-079 | LABORERFORM WORK ONLY | $30.21 | $14.57 |
| SUKS2019-079 | LABORERFLAGGER | $13.20 | $0.00 |
| SUKS2019-079 | LINE CONSTRUCTIONGROUNDMAN | $24.92 | $12.15 |
| SUKS2019-079 | LINE CONSTRUCTIONLINEMAN | $41.52 | $17.26 |
| SUKS2019-079 | LINE CONSTRUCTIONEQUIPMENT OPERATOR | $30.67 | $14.36 |
| SUKS2019-079 | OPERATORBOBCAT/SKID STEER/SKID LOADER | $34.88 | $15.40 |
| SUKS2019-079 | OPERATORBULLDOZER | $28.15 | $11.65 |
| SUKS2019-079 | OPERATORCONCRETE FINISHING MACHINE | $24.26 | $0.00 |
| SUKS2019-079 | OPERATORCONCRETE SAW | $33.87 | $15.16 |
| SUKS2019-079 | OPERATORCRANE | $30.38 | $11.08 |
| SUKS2019-079 | OPERATORGRADER/BLADE | $29.66 | $12.55 |
| SUKS2019-079 | OPERATORMATERIAL TRANSFER VEHICLE | $14.65 | $0.00 |
| SUKS2019-079 | OPERATORMECHANIC | $32.25 | $15.31 |
| SUKS2019-079 | OPERATORROTO MILL GROUNDMAN | $18.43 | $0.00 |
| SUKS2019-079 | OPERATORSCRAPER | $17.67 | $0.00 |
| SUKS2019-079 | OPERATORSCREED | $17.38 | $3.52 |
| SUKS2019-079 | OPERATORSTRIPING MACHINE | $27.27 | $12.25 |
| SUKS2019-079 | OPERATORTRACTOR | $24.28 | $0.00 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORROTO MILL | $40.17 | $22.29 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORROLLER | $40.17 | $22.29 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $40.17 | $22.29 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORLOADER | $40.17 | $22.29 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORBROOM/SWEEPER | $40.17 | $22.29 |
| ENGI0101-026 | POWER EQUIPMENT OPERATORBACKHOE/EXCAVATOR/TRACKHOE | $40.17 | $22.29 |
| SUKS2019-079 | TRAFFIC CONTROLSERVICE DRIVER | $20.00 | $12.49 |
| SUKS2019-079 | TRAFFIC SIGNALIZATIONTRAFFIC SIGNAL INSTALLATION (GROUNDMAN) | $17.10 | $0.00 |
| SUKS2019-079 | TRUCK DRIVERDUMP AND TANDEM | $29.04 | $12.45 |
| SUKS2019-079 | TRUCK DRIVERFLATBED AND LOWBOY | $28.41 | $14.05 |
| SUKS2019-079 | TRUCK DRIVEROFF ROAD TRUCK | $19.06 | $0.00 |
| TEAM0541-013 | TRUCK DRIVERWATER TRUCK | $38.04 | $15.85 |