Pulling the wage determination…
Revision 2 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Idaho: Power. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 2). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| BRID0003-003 | BRICKLAYER | $26.79 | $17.34 |
| SUID2010-027 | CARPENTER | $18.00 | $0.00 |
| SUID2010-027 | CEMENT MASON/CONCRETE FINISHER | $13.52 | $2.80 |
| ELEC0449-007 | ELECTRICIAN(INCLUDING LOW VOLTAGE WIRING) | $40.00 | $18.74 |
| SUID2010-027 | IRONWORKER, REINFORCING | $24.74 | $14.82 |
| IRON0732-002 | IRONWORKER, STRUCTURAL | $33.37 | $22.98 |
| LABO0155-006 | LABORERGROUP 4 MASON TENDER (CEMENT/CONCRETE & BRICK ) |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $33.93 |
| $16.50 |
| SUID2010-027 | LABORERCOMMON OR GENERAL | $17.87 | $0.00 |
| SUID2010-027 | OPERATORBACKHOE/EXCAVATOR | $22.23 | $0.00 |
| SUID2010-027 | OPERATORBOBCAT/SKID STEER/SKID LOADER | $16.28 | $0.00 |
| SUID2010-027 | OPERATORBULLDOZER | $24.52 | $7.87 |
| SUID2010-027 | OPERATORLOADER (FRONT END) | $21.27 | $5.54 |
| PAIN0764-001 | PAINTERBRUSH, ROLLER, AND SPRAY | $12.09 | $5.33 |
| PLUM0648-004 | PLUMBER | $36.75 | $18.93 |
| ENGI0302-038 | POWER EQUIPMENT OPERATORGROUP 3 FORKLIFT ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY | $36.33 | $16.10 |
| ENGI0302-038 | POWER EQUIPMENT OPERATORGROUP 6 CRANE (UP TO AND INCLUDING 50 TON) ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. CRANE LONG BOOM PAY: A. CRANE BOOMS, 100FT TO 150FT, FIFTEEN CENTS OVER SCALE B. CRANE BOOMS, 150 FT TO 200 FT, THIRTY CENTS OVER SCALE C. CRANE BOOMS, OVER 200 FT., FORTY-FIVE CENTS OVER SCALE | $36.98 | $16.10 |
| ENGI0302-038 | POWER EQUIPMENT OPERATORGROUP 7 CRANE (OVER 50 TONS), TOWER CRANE ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. CRANE LONG BOOM PAY: A. CRANE BOOMS, 100FT TO 150FT, FIFTEEN CENTS OVER SCALE B. CRANE BOOMS, 150 FT TO 200 FT, THIRTY CENTS OVER SCALE C. CRANE BOOMS, OVER 200 FT., FORTY-FIVE CENTS OVER SCALE | $37.35 | $16.10 |
| SUID2010-027 | ROOFER | $19.00 | $0.00 |
| SHEE0103-003 | SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION | $35.50 | $22.25 |
| SUID2010-027 | TRUCK DRIVERDUMP TRUCK | $16.06 | $0.00 |