Revision 1 · modified May 18, 2026 · published May 18, 2026 · Building
Covers 1 county in Florida: Levy. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUFL2009-056 | CARPENTER, INCLUDES FORM WORK | $14.79 | $1.81 |
| SUFL2009-056 | CEMENT MASON/CONCRETE FINISHER | $16.79 | $0.00 |
| ELEC1205-004 | ELECTRICIAN | $33.50 | $13.85 |
| IRON0597-004 | IRONWORKERSTRUCTURAL AND REINFORCING | $29.50 | $12.98 |
| SUFL2009-056 | LABORERCOMMON OR GENERAL | $9.95 | $0.00 |
| SUFL2009-056 | LABORERPIPELAYER | $11.42 | $1.95 |
| SUFL2009-056 |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| OPERATORBACKHOE/EXCAVATOR |
| $13.19 |
| $0.00 |
| SUFL2009-056 | OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $9.58 | $0.00 |
| SUFL2009-056 | PAINTERBRUSH, ROLLER AND SPRAY | $10.10 | $0.00 |
| SUFL2009-056 | PLUMBER | $12.27 | $3.33 |
| ENGI0487-031 | POWER EQUIPMENT OPERATORGROUP 3 CRANES NOT DESCRIBED ABOVE | $37.01 | $16.85 |
| ENGI0487-031 | POWER EQUIPMENT OPERATORGROUP 2 LATTICE UNDER 150 TON, 100 TON UP TO 250 TON HYDRO CRANES | $38.01 | $16.85 |
| ENGI0487-031 | POWER EQUIPMENT OPERATORGROUP 1: 150 TON LATTICE, 250 TON HYDRO, FRICTION, TOWER AND LUFFING CRANES, 300+ FT BOOM | $39.01 | $16.85 |
| SUFL2009-056 | ROOFERBUILT UP, COMPOSITION, HOT TAR AND SINGLE PLY | $12.00 | $0.00 |
| SHEE0015-002 | SHEET METAL WORKER(HVAC DUCT INSTALLATION ONLY) | $25.75 | $16.92 |
| SUFL2009-056 | TRUCK DRIVER, INCLUDES DUMP AND 10 YARD HAUL AWAY | $8.00 | $0.15 |