Revision 1 · modified May 18, 2026 · published May 18, 2026 · Residential
Covers 1 county in Arizona: Maricopa. View the source document on SAM.gov.
DOL marked this determination modified May 18, 2026 (revision 1). Line-level rate diffs begin from the next revision we observe — this determination was modified before we began tracking it, so we can’t show which lines changed. Verify the current rates on SAM.gov.
| Identifier | Classification | Base | Fringe |
|---|---|---|---|
| SUAZ2011-001 | ALARM INSTALLER, INCLUDES WIRING AND INSTALLATION | $13.91 | $0.00 |
| BRAZ0003-007 | BRICKLAYER ZONE PAY(RADIUS MILES FROM THE INTERSECTION OF CENTRAL AVE. AND WASHINGTON ST., PHOENIX, AZ) ZONE A: 0-60 MILES- BASE RATE ZONE B: 61-75 MILES- BASE RATE PLUS $2.00 PER HOUR ZONE C: 75-100 MILES- BASE RATE PLUS $3.00 PER HOUR ZONE D: 101-200 MILES- BASE RATE PLUS $3.50 PER HOUR ZONE E: OVER 200 MILES- BASE RATE PLUS $6.50 PER HOUR | $32.29 | $9.97 |
| SUAZ2011-001 | CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $18.16 | $0.00 |
| PLAS0394-006 | CEMENT MASON/CONCRETE FINISHER | $28.78 | $9.17 |
| SUAZ2011-001 | DRYWALL HANGER | $15.00 | $0.58 |
| SUAZ2011-001 | ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS |
Parsed from the SAM.gov document, synced July 18, 2026. Unparsed blocks are logged, never guessed. Verify against the source document before filing.
| $15.45 |
| $0.01 |
| SUAZ2011-001 | FORM WORKER | $14.37 | $0.00 |
| SUAZ2011-001 | GLAZIER | $13.45 | $0.00 |
| SUAZ2011-001 | HVAC MECHANIC(INSTALLATION OF HVAC DUCT) | $15.36 | $0.00 |
| IRON0075-008 | IRONWORKER, STRUCTURAL | $33.00 | $19.91 |
| SUAZ2011-001 | LABORERPIPELAYER | $13.00 | $0.00 |
| SUAZ2011-001 | LABORERCOMMON OR GENERAL | $10.18 | $0.00 |
| SUAZ2011-001 | LABORERGRADE CHECKER | $16.83 | $0.45 |
| SUAZ2011-001 | LABORERMASON TENDER - BRICK | $12.77 | $0.00 |
| SUAZ2011-001 | LABORERMASON TENDER - CEMENT/CONCRETE/STONE | $11.00 | $0.00 |
| SUAZ2011-001 | OPERATORTRACTOR | $22.63 | $0.00 |
| SUAZ2011-001 | OPERATORBACKHOE | $18.29 | $0.00 |
| SUAZ2011-001 | OPERATOREXCAVATOR | $24.67 | $0.00 |
| SUAZ2011-001 | OPERATORFORKLIFT | $16.17 | $0.00 |
| SUAZ2011-001 | OPERATORLOADER (FRONT END) | $15.00 | $0.00 |
| SUAZ2011-001 | OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $20.75 | $0.00 |
| SUAZ2011-001 | OPERATORROLLER | $16.24 | $1.42 |
| SUAZ2011-001 | OPERATORSCRAPER | $19.20 | $1.52 |
| SUAZ2011-001 | PAINTERBRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $12.89 | $0.00 |
| SUAZ2011-001 | PLUMBER | $20.14 | $4.08 |
| ENGI0428-005 | POWER EQUIPMENT OPERATORGRADER/BLADE | $34.49 | $12.57 |
| SUAZ2011-001 | ROOFER | $13.67 | $0.00 |
| SUAZ2011-001 | SPRINKLER FITTER(FIRE SPRINKLERS) | $17.73 | $0.00 |
| SUAZ2011-001 | TRUCK DRIVERDUMP TRUCK | $17.02 | $0.00 |
| SUAZ2011-001 | TRUCK DRIVERWATER TRUCK | $14.50 | $0.00 |