TRUCK DRIVER leads the heavy schedule for Millard County, UT at $46.65 base plus $15.75 fringe. The active federal wage determination covering heavy construction in Millard County, UT lists 21 classifications with published rates, base pay from $9.00 to $46.65 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK(EXCLUDES NATURAL GAS PIPELINE CONSTRUCTION FORM WORK) | $14.75 | $3.03 | UT20260020 |
| CEMENT MASON/CONCRETE FINISHER | $14.00 | $0.56 | UT20260020 |
| LABORERMASON TENDER - CEMENT/CONCRETE | $9.00 | $0.36 | UT20260020 |
| LABORERCOMMON OR GENERAL (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $10.92 |
Across the 21 published classifications for heavy work in Millard County, UT, base pay spans $9.00 to $46.65 per hour with a median of $20.59.
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
This schedule mixes sources: 52% of lines carry union identifiers and the rest are survey-based. Two crews on one site can be governed by rates that update on entirely different rhythms.
A wage determination is cited as number plus modification, for example UT20260020 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| $0.00 |
| UT20260020 |
| LABORERPIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $9.00 | $0.00 | UT20260020 |
| LABORER CHAIN SAW AND POWER DRILLNATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 | UT20260020 |
| LABORER COMMON OR GENERAL, NAIL GUN, PIPELAYER, POT TENDERNATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.59 | $8.65 | UT20260020 |
| LABORER FORMWORKERNATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 | UT20260020 |
| LABORER POWDERMANNATURAL GAS PIPELINE CONSTRUCTION ONLY | $21.65 | $8.65 | UT20260020 |
| LABORER SANDBLASTERNATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 | UT20260020 |
| OPERATORPOWER EQUIPMENT (3) BACKHOE/EXCAVATOR | $30.78 | $16.09 | UT20260020 |
| OPERATORPOWER EQUIPMENT OILER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $22.03 | $11.88 | UT20260020 |
| OPERATORPOWER EQUIPMENT BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, CRANE, MECHANIC, TRENCHER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $35.68 | $17.57 | UT20260020 |
| OPERATORGRADER/BLADE, EXCLUDES NATURAL GAS PIPELINE CONSTRUCTION | $13.61 | $0.00 | UT20260020 |
| OPERATORLOADER (FRONT END) | $11.38 | $0.00 | UT20260020 |
| OPERATORROLLER (DIRT AND GRADE COMPACTION) | $10.89 | $0.00 | UT20260020 |
| OPERATORTRACKHOE (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $13.63 | $0.00 | UT20260020 |
| TRUCK DRIVER(EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $12.00 | $0.00 | UT20260020 |
| TRUCK DRIVERGROUP 3 AMBULANCE , BUS, DUMP TRUCK (2 AND 3 AXLE), FLATBED TRUCK (2 AND 3 AXLE), GREASE TRUCK, HOT PASS TRUCK (3 AXLE), JEEP, PICK-UP, SINGLE AXLE FLOAT (3 AXLE), SKID TRUCK (2 AND 3 AXLE), STATION WAGON, STRINGER BEAD & HOT PASS (2 AXLE), SWAMP BUGGY/ MARSH BUGGY, OR SIMILAR TYPE EQUIPMENT, TEAM DRIVER, WATER TRUCK (2 AND 3 AXLE) NATURAL GAS PIPELINE CONSTRUCTION ONLY PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE FOR THE FOLLOWING CLASSIFICATIONS GROUP 1: LOW BOY AND TRUCK MECHANIC GROUP 2: STRINGE | $41.90 | $15.75 | UT20260020 |
| TRUCK DRIVERNATURAL GAS PIPELINE CONSTRUCTION ONLY: GROUP 2 STRINGER TRUCK PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE | $46.02 | $15.75 | UT20260020 |
| TRUCK DRIVERNATURAL GAS PIPELINE CONSTRUCTION ONLY: GROUP 1 LOW BOY AND TRUCK MECHANIC PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE | $46.65 | $15.75 | UT20260020 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.