ELEVATOR MECHANIC PAID HOLIDAYS leads the building schedule for Greene County, OH at $57.41 base plus $38.44 fringe. The active federal wage determination covering building construction in Greene County, OH lists 34 classifications with published rates, base pay from $21.02 to $57.41 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $35.23 | $23.04 | OH20260081 |
| BRICKLAYER | $33.30 | $18.28 | OH20260081 |
| CARPENTER | $30.96 | $18.44 | OH20260081 |
| CEMENT MASON/CONCRETE FINISHER | $32.71 | $19.27 | OH20260081 |
| DRYWALL HANGER AND METAL STUD INSTALLER |
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
With 34 classifications carrying published rates, this is a comparatively deep schedule; most trades a building project needs appear without a conformance request.
This schedule mixes sources: 65% of lines carry union identifiers and the rest are survey-based. Two crews on one site can be governed by rates that update on entirely different rhythms.
A wage determination is cited as number plus modification, for example OH20260081 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| $21.02 |
| $4.21 |
| OH20260081 |
| ELECTRICIAN | $38.00 | $22.49 | OH20260081 |
| ELEVATOR MECHANIC PAID HOLIDAYSA. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $57.41 | $38.44 | OH20260081 |
| FORM WORKER | $22.41 | $9.01 | OH20260081 |
| GLAZIER | $31.95 | $18.20 | OH20260081 |
| IRONWORKERORNAMENTAL | $37.77 | $23.90 | OH20260081 |
| IRONWORKER(REINFORCING AND STRUCTURAL) | $37.39 | $25.35 | OH20260081 |
| LABORERMASON TENDER - BRICK | $27.30 | $18.75 | OH20260081 |
| LABORERCOMMON OR GENERAL; ASBESTOS ABATEMENT (REMOVAL FROM CEILINGS, FLOORS, AND WALLS) | $31.65 | $12.95 | OH20260081 |
| LABORERPIPELAYER | $23.98 | $8.58 | OH20260081 |
| LABORERMASON TENDER - CEMENT/CONCRETE | $22.95 | $8.60 | OH20260081 |
| OPERATORROLLER | $28.25 | $12.61 | OH20260081 |
| OPERATORPAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $30.28 | $13.29 | OH20260081 |
| OPERATORBULLDOZER | $26.01 | $4.95 | OH20260081 |
| OPERATORBOBCAT/SKID STEER/SKID LOADER | $30.26 | $12.58 | OH20260081 |
| OPERATORLOADER | $29.99 | $12.80 | OH20260081 |
| PAINTERBRUSH AND ROLLER | $29.15 | $13.97 | OH20260081 |
| PAINTERSPRAY | $22.78 | $12.40 | OH20260081 |
| PIPEFITTER(EXCLUDES HVAC PIPE INSTALLATION) | $51.00 | $32.56 | OH20260081 |
| PLUMBER(INCLUDES HVAC PIPE INSTALLATION) | $43.05 | $27.18 | OH20260081 |
| POWER EQUIPMENT OPERATORCRANE | $44.14 | $16.41 | OH20260081 |
| POWER EQUIPMENT OPERATORGRADER/BLADE | $32.42 | $19.66 | OH20260081 |
| POWER EQUIPMENT OPERATORFORKLIFT | $28.87 | $19.66 | OH20260081 |
| POWER EQUIPMENT OPERATOR(MECHANIC) | $32.92 | $19.66 | OH20260081 |
| ROOFER | $34.38 | $19.94 | OH20260081 |
| SHEET METAL WORKER(HVAC DUCT AND HVAC UNIT INSTALLATION ONLY) | $26.41 | $17.34 | OH20260081 |
| SPRINKLER FITTER(FIRE SPRINKLERS) | $48.28 | $28.08 | OH20260081 |
| TILE FINISHER | $28.28 | $11.05 | OH20260081 |
| TILE SETTER | $30.98 | $15.82 | OH20260081 |
| TRUCK DRIVERDUMP (ALL TYPES) | $22.08 | $11.51 | OH20260081 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.