Highway prevailing wage rates for Wyoming County, NY | PrevailWage
Highway prevailing wage rates for Wyoming County, NY
ELECTRICIAN, LINE CONSTRUCTION leads the highway schedule for Wyoming County, NY at $64.59 base plus $42.92 fringe. The active federal wage determination covering highway construction in Wyoming County, NY lists 71 classifications with published rates, base pay from $14.20 to $64.59 per hour. The determination was last modified May 18, 2026.
The highest published base on this schedule belongs to ELECTRICIAN, LINE CONSTRUCTION at $64.59 per hour plus $42.92 fringe; the schedule's median base is $41.19.
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
100% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
Using these rates
Read the modification number
A wage determination is cited as number plus modification, for example NY20260041 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Put the WD in your bid file
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
Check rates the Friday before payroll
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
Match classifications by duties, not titles
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
Fringe crediting basics
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
Statement of Compliance wording
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Questions
Which wage determination applies to my project in Wyoming County?
The wage determination incorporated into your contract is the one that governs, per 29 CFR 1.6. For new highway work in Wyoming County, NY, the current active determination is NY20260041. Verify with your contracting officer before bidding or paying.
How often do these rates change?
DOL publishes wage determination modifications weekly, generally on Fridays. The determination behind this page was last modified May 18, 2026.
What is the difference between the base rate and the fringe rate?
The base rate is the minimum hourly wage; the fringe amount is an additional hourly benefit obligation you can meet with bona fide benefit contributions or pay in cash. On this schedule the median fringe is about 72% of base.
My classification is not listed for Wyoming County. What do I do?
If the work classification you need is not on the determination, the contractor requests a conformance (additional classification and rate) through the contracting agency using Standard Form 1444. Do not substitute a similar-sounding classification.
What counts as highway construction?
Highway covers roads, streets, runways, and similar paving work not incidental to building, residential, or heavy construction.
Does the federal rate or the New York state prevailing wage apply?
COMMUNICATIONS SYSTEM(MASTER TECHNICIAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYS
COMMUNICATIONS SYSTEM(CABLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTER
COMMUNICATIONS SYSTEM(INSTALLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, IN
COMMUNICATIONS SYSTEM(SOUND WIREMAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS
ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY
ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMP
ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFOR
ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY
ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY B
ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)
ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)
ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab
ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)
ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat
ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)
ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins
ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION ANDMAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITE
ELECTRICIAN LINE CONSTRUCTION SUBSTATIONGROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARYINSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRE
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTCABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTGROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTINSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
LABORERSGROUP 2 LABORERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
LABORERSGROUP 1 FLAGGERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
LABORERSGROUP 5 HAZARDOUS WASTE REMOVAL FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
LABORERSGROUP 4 BLASTERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
LABORERSGROUP 3 RAKERS, DRILLERS, PIPELAYERS, AND TORCH OPERATORS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
POWER EQUIPMENT OPERATORSGROUP 3 CRANES 5 - 60 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY
POWER EQUIPMENT OPERATORSGROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS (4 OR LESS), COMPRESSORS: (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS, DUST COLLECTORS, GENERATORS, MECHANICAL HEATERS, PUMPS, WELDING MACHINES (FOUR OF ANY TYPE OR COMBINATION), CONCRETE MIXER (1/2 CU. YD. AND UNDER), FIREMAN, FORM TAMPER, FUEL TRUCK, HEATING BOILER (USED FOR TEMPRORY HEAT), JEEP TRENCHER, POWER HEATERMAN, POWER PLANT IN EXCESS OF 10 K.W., PUM
POWER EQUIPMENT OPERATORSGROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT (100 FT. OR LESS), ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER, AUTOMATIC FINE GRADE MACHINE (CMI AND SIMILAR TYPE), ARCHER HOIST, BACKHOE AND PULL HOE (TRACTOR MOUNTED AND RUBBER MOUNTED), BACK FILLING MACHINE, BELT PLACE (CMI AND SIMILAR), BENDING MACHINE (PIPE), BITUMINOUS SPREADER AND MIXER, BLACK TOP PLANT (AUTOMATED), BLACK TOP PLANT (NON-AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACK MOUNTED), BLOWER FOR BURN
POWER EQUIPMENT OPERATORSGROUP 7 MASTER MEACHANIC NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY
POWER EQUIPMENT OPERATORSGROUP 6 CRANES 400 TONS & OVER NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY
POWER EQUIPMENT OPERATORSGROUP 5 CRANES 200 - 399 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY
POWER EQUIPMENT OPERATORSGROUP 4 CRANES 61 - 199 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DAY; B-MEMORIAL DAY; C-INDEPENDENCE DAY; D-LABOR DAY; THANKSGIVING DAY; F-CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY
TRUCK DRIVERSGROUP 5 OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE-HITCHED EQUIPMENT SHERE NOT SELF-LOADED. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY
TRUCK DRIVERSGROUP 2 TANDEMS; BATCH TRUCK; MECHANICS. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY
TRUCK DRIVERSGROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY
TRUCK DRIVERSGROUP 3 SEMI-TRAILERS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC; FUEL TRUCK. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY
TRUCK DRIVERSGROUP 4 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE UNIT. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY
TRUCK DRIVERS((GENESEE COUNTY: TOWNSHIPS OF ALABAMA, PEMBROKE, AND DARIEN) (ORLEANS COUNTY: TOWNSHIPS OF YATES, RIDGEWAY, AND SHELBY) (WYOMING COUNTY: TOWNSHIPS OF BENNINGTON, SHELDON, JAVA, AND ARCADE))
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.
They are separate systems. Davis-Bacon rates apply to federally funded or assisted work; a state prevailing wage law can apply to state-funded work. A project can be covered by both, in which case the higher rate for each classification effectively controls. This page shows the federal determination only.
Is the WH-347 form mandatory?
The WH-347 itself is optional; what is mandatory on covered work is submitting weekly certified payroll with the same information and a signed Statement of Compliance. Most contractors use the WH-347 layout because agencies expect it.