ELECTRICIAN, LINE CONSTRUCTION leads the heavy schedule for Schuyler County, NY at $64.59 base plus $42.92 fringe. The active federal wage determinations covering heavy construction in Schuyler County, NY list 156 classifications with published rates, base pay from $14.20 to $64.59 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| ASBESTOS/INSULATOR WORKER(INCLUDES APPLICATION OF ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT.) | $43.25 | $27.29 | NY20260005 |
| BOILERMAKER | $39.35 | $33.18 | NY20260005 |
| BUILDING CONSTRUCTIONMARBLE, TILE AND TERRAZZO FINISHERS (CORNING CHAPTER) | $34.44 | $20.38 | NY20260005 |
Across the 156 published classifications for heavy work in Schuyler County, NY, base pay spans $14.20 to $64.59 per hour with a median of $42.11.
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
92% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
A wage determination is cited as number plus modification, for example NY20260001 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| BUILDING CONSTRUCTIONBRICKLAYERS, CEMENT MASONS, STONE MASONS, POINTERS, CAULKERS AND CLEANERS (CORNING CHAPTER) |
| $33.26 |
| $30.21 |
| NY20260005 |
| BUILDING CONSTRUCTIONMARBLE MASON, TILE LAYERS AND TERRAZZO WORKERS (CORNING CHAPTER) | $34.69 | $25.76 | NY20260005 |
| CABLE SPLICER(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)) | $36.73 | $23.39 | NY20260048 |
| CABLE SPLICER(ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $35.75 | $20.68 | NY20260048 |
| CARPENTER | $20.61 | $7.49 | NY20260048 |
| CARPENTER, BUILDING CONSTRUCTION(CHEMUNG COUNTY) | $31.59 | $23.24 | NY20260005 |
| CARPENTER, HEAVY & HIGHWAY CONSTRUCTION(CHEMUNG COUNTY) | $39.52 | $27.16 | NY20260005 |
| CARPENTER, HIGHWAY CONSTRUCTION(SCHUYLER COUNTY) | $39.52 | $27.16 | NY20260005 |
| CARPENTER, MILLWRIGHTS & PILEDRIVERS, BUILDING CONSTRUCTION(CHEMUNG COUNTY) | $31.59 | $23.24 | NY20260005 |
| CEMENT MASON/CONCRETE FINISHERHEAVY AND HIGHWAY CONSTRUCTION (CORNING CHAPTER) | $38.63 | $25.05 | NY20260005 |
| CEMENT MASON/CONCRETE FINISHER | $17.45 | $7.90 | NY20260048 |
| COMMUNICATIONS SYSTEM(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRA | $14.20 | $14.02 | NY20260048 |
| COMMUNICATIONS SYSTEM, INSTALLER(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRA | $22.90 | $21.38 | NY20260048 |
| COMMUNICATIONS SYSTEM, MASTER TECHNICIAN(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRA | $44.50 | $36.05 | NY20260048 |
| COMMUNICATIONS SYSTEM, SOUND WIREMAN(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRA | $44.50 | $36.05 | NY20260048 |
| DREDGINGCLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; | $41.93 | $14.90 | NY20260001 |
| DREDGINGCLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $ | $48.48 | $15.34 | NY20260001 |
| DREDGINGCLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $ | $43.20 | $14.99 | NY20260001 |
| DREDGINGCLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DEC | $39.46 | $14.73 | NY20260001 |
| DREDGINGCLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLAS | $30.86 | $14.15 | NY20260001 |
| DREDGINGCLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHA | $37.15 | $14.57 | NY20260001 |
| DREDGINGCLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICAT | $38.38 | $14.66 | NY20260001 |
| ELECTRICIAN(CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)) | $44.50 | $36.06 | NY20260048 |
| ELECTRICIAN(CORTLAND AND TOMPKINS COUNTIES) | $50.50 | $35.03 | NY20260048 |
| ELECTRICIAN(WYOMING (REMAINDER OF COUNTY)) | $44.30 | $30.20 | NY20260048 |
| ELECTRICIAN(ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $42.50 | $27.23 | NY20260048 |
| ELECTRICIAN(CHEMUNG COUNTY) | $43.40 | $31.72 | NY20260005 |
| ELECTRICIAN(ALLEGANY (REMAINDER OF COUNTY), SCHUYLER (REMAINDER OF COUNTY) AND STEUBEN COUNTIES) | $43.40 | $31.72 | NY20260048 |
| ELECTRICIAN(SENECA (TOWNSHIPS OF COVERT AND LODI) AND SCHUYLER (TOWNSHIPS OF CATHARINE, CAYUTA, HECTOR)) | $44.50 | $31.89 | NY20260048 |
| ELECTRICIAN(SCHUYLER COUNTY (TOWNSHIPS OF CATHARINE, CAYUTA AND HECTOR)) | $44.50 | $31.89 | NY20260005 |
| ELECTRICIAN(SENECA (REMAINDER OF COUNTY) AND YATES COUNTY) | $45.00 | $31.12 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFOR | $52.86 | $35.60 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $42.29 | $30.66 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMP | $47.57 | $31.03 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $31.72 | $29.87 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $31.72 | $29.87 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFOR | $52.86 | $35.60 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMP | $47.57 | $31.03 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $42.29 | $30.66 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY B | $42.29 | $30.66 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY B | $42.29 | $30.66 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Substation:) | $63.14 | $33.82 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Substation:) | $35.34 | $30.12 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Substation:) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Substation:) | $63.14 | $33.82 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Substation:) | $35.34 | $30.12 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Substation:) | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION ANDMAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITE | $61.56 | $36.21 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION ANDMAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITE | $61.56 | $36.21 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATIONGROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATIONGROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARYINSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRE | $49.25 | $31.15 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARYINSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRE | $49.25 | $31.15 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTCABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTGROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTINSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | NY20260048 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTINSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTGROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | NY20260005 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTCABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | NY20260005 |
| ELEVATOR MECHANIC(CHEMUNG COUNTY:) FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $58.44 | $38.44 | NY20260005 |
| GLAZIER | $30.00 | $31.95 | NY20260005 |
| HAZARDOUS MATERIAL HANDLER(SCOPE OF WORK: DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEM) | $38.50 | $25.04 | NY20260005 |
| IRONWORKERSTRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRET ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN WELDER, SHEETER, SHEETER BUCKER-UP (SCHUYLER COUNTY (TOWNSHIPS OF CATHARINE, CAYUTA, HECTOR AND MONTOUR)) | $37.16 | $30.68 | NY20260005 |
| IRONWORKERS: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER-RIGGER, FENCE ERECTOR, PRE-CAST CONCRETE ERECTOR, REINFORCING, STONE DERRICKMAN (CHEMUNG; SCHUYLER (TWPS. OF DIX, ORANGE, REDING AND TRYON).) | $35.75 | $30.80 | NY20260005 |
| IRONWORKERS: SHEETER (CHEMUNG; SCHUYLER (TWPS. OF DIX, ORANGE, REDING AND TRYON).) | $36.00 | $30.80 | NY20260005 |
| LABORER GROUP 1(CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY (ZONE III))LABORER GROUP 1 (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY (ZONE III)) | $33.00 | $22.51 | NY20260005 |
| LABORER GROUP 1-(ZONE III) (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY)LABORER GROUP 1-(ZONE III) (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY) | $33.00 | $22.51 | NY20260005 |
| LABORER GROUP 2(CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY (ZONE III))LABORER GROUP 2 (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY (ZONE III)) | $33.20 | $22.51 | NY20260005 |
| LABORER GROUP 2(ZONE III) (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY)LABORER GROUP 2 (ZONE III) (CHEMUNG AND SCHUYLER (EXCEPT CATHERINE TOWNSHIP): HEAVY & HIGHWAY) | $33.20 | $22.51 | NY20260005 |
| LABORERSHEAVY & HIGHWAY: GROUP 5 TOXIC WASTE REMOVAL SCHUYLER (TWPS. OF CATHERINE - INCLUDING THE VILLAGE OF ODESSA) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $38.76 | $25.60 | NY20260005 |
| LABORERSHEAVY & HIGHWAY: GROUP 3 ALL ROCK OR DRILL MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE); ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN SCHUYLER (TWPS. OF CATHERINE - INCLUDING THE VILLAGE OF ODESSA) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.96 | $25.60 | NY20260005 |
| LABORERSHEAVY & HIGHWAY: GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTAR MIXER; PAVEMENT BREAKER; HANDLERS OF ALL STEEL MESH; SMALL GENERATORS FOR LABORERS' TOOLS; INSTALLATION OF BRIDGE DRAINAGE PIPE; PIPELAYERS; VIBRATOR TYPE ROLLERS; TAMPERS; DRILL DOCTOR; TAIL OR SCREW OPERATOR ON ASPHALT PAVER; WATER PUMP OPERATOR (1-1/2"" AND SINGLE DIAPHRAM); NOZZLE (ASPHALT, GUNNITE, SEEDING AND SANDBLASTING); LABORERS | $35.76 | $25.60 | NY20260005 |
| LABORERSHEAVY & HIGHWAY: GROUP 1 LABORERS; FLAGGERS; OUTBOARD AND HAND BOATS SCHUYLER (TWPS. OF CATHERINE - INCLUDING THE VILLAGE OF ODESSA) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.56 | $25.60 | NY20260005 |
| LABORERSHEAVY & HIGHWAY: GROUP 4 BLASTERS; FORM SETTERS; STONE OR GRANITE CURB SETTERS SCHUYLER (TWPS. OF CATHERINE - INCLUDING THE VILLAGE OF ODESSA) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $36.16 | $25.60 | NY20260005 |
| LABORERSPIPELAYERS | $17.79 | $6.70 | NY20260048 |
| LABORERSUNSKILLED | $17.20 | $6.63 | NY20260048 |
| LABORERS(RAKERS) | $17.04 | $6.30 | NY20260048 |
| OPERATING ENGINEERGROUP 2 (EXCAVATING AND PAVING) BACKHOE (TRACTOR MOUNTED, RUBBER TIRED); BITUMINOUS SPREADER AND MIXER; BLACKTOP PLANT (NON AUTOMATED); BORING MACHINE; CAGE HOIST; CENTRAL MIX PLANT (NON AUTOMATED) AND ALL CONCRETE BATCHING PLANTS; CHERRY PICKER, 5 TONS AND UNDER; COMPRESSOR (4 OR LESS) EXCEEDING 2000 CFM COMBINED CAPACITY; CONCRETE PAVER OVER 16S; CONCRETE PUMP; CRUSHER; DRILL RIGS (TRACTOR MOUNTED); FRONT END LOADER (UNDER 4 CU. YDS); HI- PRESSURE BOILER (15 LBS AND OVER); HOIST (ONE DRUM); KO | $40.79 | $34.85 | NY20260005 |
| OPERATING ENGINEERGROUP 1 (EXCAVATING AND PAVING) ASPHALT PAVER; AUTOMATIC FINE GRADER; BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED); BLACKTOP PLANT (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX CONCRETE PLANT (AUTOMATED); CHERRY PICKER- OVER 5 TON CAPACITY; CRANE; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DUAL DRUM PAVER; FRONT END LOADER (4 CU. YD. AND OVER); HOIST,(TOW OR 3 DRUM); PILE DRIVER; POWER GRADER WITH ELEVATION LOADER ATTACHMENT; QUARRY MASTER (OR EQUIVALENT); SHOVEL; SLIP FORM PAVER; TRA | $41.26 | $34.85 | NY20260005 |
| OPERATING ENGINEERGROUP 1 (HEAVY AND HIGHWAY) AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT); AUTOMATED FINE GRADE MACHINE (CMI); BACKHOE; BELT PLACER (CMI OR SIMILAR); BLACKTOP SPREADER (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX PLANT (AUTOMATED); CHERRY PICKER (5 TONS); CONCRETE CURB MACHINE (SELF-PROPELLED SLIPFORM); CONCRETE PUMP; CRANE; CRANE SHAFT; CRANE UNDERGROUND; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DREDGE; DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILA | $55.38 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 1 (TUNNEL AND SHAFT) AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT); AUTOMATED FINE GRADE MACHINE (CMI); BACKHOE; BELT PLACER (CMI OR SIMILAR); BLACKTOP SPREADER (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX PLANT (AUTOMATED); CHERRY PICKER (5 TONS); CONCRETE CURB MACHINE (SELF-PROPELLED SLIPFORM); CONCRETE PUMP; CRANE; CRANE SHAFT; CRANE UNDERGROUND; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DREDGE; DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILAR | $58.43 | $35.00 | NY20260005 |
| OPERATING ENGINEERGROUP 2 (HEAVY AND HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDE | $54.68 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 2 (TUNNEL AND SHAFT): AUTOMATED CENTRAL MIX CONCRETE PLANT; BACKHOE (TOPSIDE); BACKHOE (TRACTOR MOUNTED,RUBBER TIRED); BITUMINOUS SPREADER AND MIXER; BLACKTOP PLANT (NON AUTOMATED); BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED); BORING MACHINE; CAGE HOIST; CENTRAL MIX PLANT (NON AUTOMATED) AND ALL CONCRETE BATCHING PLANTS; CHERRY PICKER (5 TONS CAPACITY AND UNDER); COMPRESSORS (4 OR LESS EXCEEDING 2000 CFM COMBINED CAPACITY); CONCRETE PAVER (OVER 16S); CONCRETE PUMP; CRANE (TOPSIDE); CR | $57.21 | $35.00 | NY20260005 |
| OPERATING ENGINEERGROUP 3 (EXCAVATING AND PAVING) COMPRESSORS (4 NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR 3 OR LESS WITH MORE THAN 1200 CFM BUT NOT TO EXCEED 2000 CFM); COMPRESSORS (ANY SIZE BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS); DUST COLLECTORS; GENERATORS; WELDING MACHINES (4 OF ANY TYPE OR COMBINATION); CONCRETE PAVEMENT SPREADERS AND FINISHERS; CONVEYOR; DRILL (CORE); DRILL (WELL); ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS; FARM TRACTOR WITH ACCESSORIES; FINE GRADE MACHINE; FORK | $40.10 | $34.85 | NY20260005 |
| OPERATING ENGINEERGROUP 3 (HEAVY AND HIGHWAY): A FRAME WINCH HOIST ON TRUCK , ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-ON BOILER (USED IN CONJUNCTION WITH PRODUCTION), BITUMINOUS HEATER, SELF-PROPELLED, BOAT (POWERED), CEMENT AND BIN OPERATOR, COMPRESSORS, DUST COLLECTORS, GENERATORS, PUMPS, WELDING MACHINES, LIGHT PLANTS, HEATERS (HANDS-OFF EQUIPMENT), CONCRETE PAVEMENT SPREADER AND FINISHER, CONCRETE PAVER OR MIXER (16S AND UNDER), CONCR | $51.80 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 3 (TUNNEL AND SHAFT): ""A"" FRAME TRUCK; BALLAST REGULATOR (RIDE ON); COMPRESSORS (4 NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR 3 OR LESS WITH MORE THAN 1200 CFM BUT NOT TO EXCEED 2000 CFM); COMPRESSORS (ANY SIZE BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS; DUST COLLECTORS; GENERATORS; PUMPS; WELDING MACHINES; LIGHT PLANTS (4 OF ANY TYPE OR COMBINATION); CONCRETE PAVEMENT SPREADERS AND FINISHERS; CONVEYOR; DRILL (CORE); DRILL (WELL); ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT | $54.42 | $35.00 | NY20260005 |
| OPERATING ENGINEERGROUP 4 (EXCAVATING AND PAVING) COMPRESSOR (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS); DUST COLLECTORS; GENERATORS; WELDING MACHINES (3 OR LESS OF ANY TYPE OR COMBINATION); CONCRETE MIXER (16S AND UNDER), CONCRETE SAW-SELF PROPELLED; FIREMAN; FORM TAMPER; MULCHING MACHINE; POWER HEATERMAN; PUMPS REGARDLESS OF MOTIVE POWER NO MORE THAN 3 IN NUMBER NOT TO EXCEED 12"" IN TOTAL CAPACITY; REVINIUS WIDENER; STEAM CLEANER; TRACTOR FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DA | $36.61 | $34.85 | NY20260005 |
| OPERATING ENGINEERGROUP 4 (HEAVY AND HIGHWAY)TOWER CRANES FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $61.38 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 4 (TUNNEL AND SHAFT): CRANE, FRICTION OR LATTICE TYPE WITH BOOM LENGTH 200 FEET AND OVER FOOTNOTE: B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $51.41 | $35.00 | NY20260005 |
| OPERATING ENGINEERGROUP 5 (HEAVY AND HIGHWAY) GROUP 5: CRANES 50 TONS AND OVER FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $59.88 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 6 (HEAVY AND HIGHWAY) CRANES 49 TONS AND FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $58.38 | $35.75 | NY20260005 |
| OPERATING ENGINEERGROUP 7 (HEAVY AND HIGHWAY) MASTER MECHANIC FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $56.81 | $35.75 | NY20260005 |
| OPERATING ENGINEERMASTER MECHANIC (EXCAVATING AND PAVING). FOR EXCAVATION AND PAVING: FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | $43.26 | $34.85 | NY20260005 |
| OPERATING ENGINEERMASTER MECHANIC (TUNNEL AND SHAFT). FOR EXCAVATION AND PAVING: FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | $60.84 | $35.00 | NY20260005 |
| PAINTERS(PAPER OR VINYL HANGERS) | $27.44 | $23.78 | NY20260005 |
| PAINTERS(SPRAY WORK/SPRAY EPOXY, SWING CHAIR OR SWING SCAFFOLD) | $27.13 | $23.78 | NY20260005 |
| PAINTERS(STEEPLEJACK) | $28.13 | $23.78 | NY20260005 |
| PAINTERS(STRUCTURAL STEEL, EPOXY BRUSH OR ROLL) | $27.38 | $23.78 | NY20260005 |
| PAINTERS(PAINTERS) | $26.13 | $23.78 | NY20260005 |
| PAINTERS(SAND BLASTING/STEAM CLEANING, ACID OR HIGH PRESSURE WATER) | $27.13 | $23.78 | NY20260005 |
| PLUMBER, PIPEFITTER, STEAMFITTERINCLUDING HVAC WORK (REMAINING TOWNSHIPS) | $35.51 | $24.57 | NY20260005 |
| POWER EQUIPMENT OPERATORPAVERS (CORTLAND, SENECA AND TOMPKINS COUNTIES) A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $40.80 | $25.15 | NY20260048 |
| POWER EQUIPMENT OPERATORS: PAVERS (CATTARAUGUS AND WYOMING COUNTIES) A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $47.39 | $36.89 | NY20260048 |
| POWER EQUIPMENT OPERATORSPAVER (ALLEGANY, SCHUYLER, STEUBEN AND YATES COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $40.80 | $28.25 | NY20260048 |
| POWER EQUIPMENT OPERATORSGROUP 4 (BUILDING CONSTRUCTION) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $39.64 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 5 (BUILDING CONSTRUCTION) CRANES UP TO AND INCLUDING 25 TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $47.64 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 6 (BUILDING CONSTRUCTION) CRANES 25-250 TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $49.64 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 7 (BUILDING CONSTRUCTION) CRANES 251 AND OVER TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $50.64 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 8 (BUILDING CONSTRUCTION) TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $50.14 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 3 (BUILDING CONSTRUCTION) ANY COMBINATION (NOT TO EXCEED THREE (3) PIECES OF EQUIPMENT) COMPRESSORS �THREE (3) OR LESS, OR NOT TO EXCEED 1200 CFM COMBINED CAPACITY, FIREMAN, LONGITUDINAL FLOAT, MECHANICAL HEATER PUMPS (REGARDLESS OF MOTIVE POWER) NO MORE THAN THREE (3) IN NUMBER, NOT TO EXCEED TWELVE (12) INCHES TOTAL CAPACITY, ROLLER (FILL AND GRADE)RUBBER TIRED TRACTOR WELDING MACHINE OR MECHANICAL CONVEYOR (OVER 12FT. IN LENGTH) EXCEPTION: SINGLE GASOLINE DRIVEN WELDING MACHINE UP TO 30 | $39.64 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 2 (BUILDING CONSTRUCTION) A-FRAME TRUCK, BACKFILLING MACHINE, BACKHOE -TRACTOR MOUNTED, BARBER GREEN AND SIMILAR TYPE MACHINES, BELT CRETE AND SIMILAR TYPE MACHINES, BITUMINOUS SPREADING MACHINE 3/8 YD. CAPACITY OR LESS(FACTORY RATING), BULLDOZER, CARRY-ALL TYPE SCRAPER, COMPRESSORS: FOUR (4) NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR THREE (3) OR LESS WITH MORE THAN1200 CFM BUT NOT TO EXCEED 2000 CFM, CONCRETE MIXER, CONCRETE PLACER, CONCRETE PUMP, DINKY LOCOMOTIVES (ALL TYPES), ELEVATI | $42.34 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSGROUP 1 (BUILDING CONSTRUCTION) AIR TUGGER, ALL TERRAIN TELESCOPING MATERIAL HANDLER, CLAMSHELL, DRAGLINE, SHOVEL AND SIMILAR MACHINES OVER THREE EIGHTHS CU.YD. CAPACITY (FACT. RATING);CARRIER MOUNTED BACKHOES THAT SWING 360 DEGREES BIG GENERATOR PLANT HOIST (ON STEEL ERECTION) BRIDGE CRANE (ALL TYPES), CABLEWAY, CAISSON AUGER AND SIMILAR TYPE MACHINE, CRANE, DERRICK, DREDGE, EXCAVATOR ALL PURPOSE HYDRAULICALLY OPERATED, FORKLIFT (WITH FACTORY RATING OF FIFTEEN FT. OR MORE OF LIFT),HOIST (ON STE | $43.14 | $35.20 | NY20260005 |
| POWER EQUIPMENT OPERATORSBULLDOZERS | $22.28 | $11.79 | NY20260048 |
| POWER EQUIPMENT OPERATORS(LOADERS) | $22.10 | $11.44 | NY20260048 |
| POWER EQUIPMENT OPERATORS(EXCAVATORS) | $22.63 | $12.14 | NY20260048 |
| POWER EQUIPMENT OPERATORS(ROLLERS) | $21.08 | $11.73 | NY20260048 |
| POWER EQUIPMENT OPERATORSBACKHOES | $22.08 | $11.31 | NY20260048 |
| POWER EQUIPMENT OPERATORS(TRACTORS) | $20.57 | $10.95 | NY20260048 |
| ROOFER | $30.50 | $19.84 | NY20260005 |
| SHEET METAL WORKER | $35.94 | $20.89 | NY20260005 |
| SPRINKLER FITTER | $47.85 | $28.94 | NY20260005 |
| TRUCK DRIVERDUMP | $16.94 | $7.11 | NY20260048 |
| TRUCK DRIVER GROUP 1 FLAT BED TRUCK(SINGLE AXLE); DUMP TRUCKS (UNDER 10 YDS SINGLE AXLE); STAKE BODY TRUCK (SINGLE AXLE); DUMPSTER (SINGLE AXLE) FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $25.96 | $15.91 | NY20260005 |
| TRUCK DRIVER GROUP 2 DUMP TRUCK(OVER 10 YDS); TRANSIT MIX (UNDER 5 YDS); TRANSIT MIX (OVER 5 YDS); FLAT OR STAKE BODY (TANDEM); A-FRAME/WINCH TRUCKS; DRY BATCH TRUCK; TRUCK MOUNTED SWEEPER AND VAC TRUCKS; DUMPSTER (TANDEM) FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $26.03 | $15.91 | NY20260005 |
| TRUCK DRIVER GROUP 3 EUCLID-TYPE; OFF HIGHWAY EQUIPMENT-BACK OR DOUBLE BOTTOM DUMP TRUCKS(OVER 20 TONS); STRADDLE TRUCKS; PUSHER; ARTICULATE DUMPED TRUCKS; LOW BOY TRAILERS; SEMI TRAILERS; ASPHALT DISTRIBUTORS; FUEL TRUCK FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $26.52 | $15.91 | NY20260005 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.