ELECTRICIAN, LINE CONSTRUCTION leads the highway schedule for Livingston County, NY at $64.59 base plus $42.92 fringe. The active federal wage determination covering highway construction in Livingston County, NY lists 87 classifications with published rates, base pay from $20.53 to $64.59 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR((INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO, THE APPLICATION OF FIRESTOOPING MATERIAL OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT)) | $40.26 | $25.41 | NY20260030 |
| BOILERMAKER | $39.35 | $33.18 | NY20260030 |
| BRICKLAYERS, STONE MASONS, PLASTERERS, CEMENT MASONS, POINTER, CLEANER AND CAULKERS(BUILDING CONSTRUCTION) (ROCHESTER CHAPTER) | $35.81 | $27.65 | NY20260030 |
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
With 87 classifications carrying published rates, this is a comparatively deep schedule; most trades a highway project needs appear without a conformance request.
100% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
A wage determination is cited as number plus modification, for example NY20260030 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| CARPENTERSHEAVY & HIGHWAY CONSTRUCTION FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $38.18 | $26.11 | NY20260030 |
| CARPENTERSPILEDRIVERS (BUILDING CONSTRUCTION) | $29.00 | $18.89 | NY20260030 |
| CARPENTERSPILEDRIVERS (HEAVY & HIGHWAY CONSTRUCTION) | $29.00 | $18.89 | NY20260030 |
| CARPENTERS, INCLUDING DRYWALL HANGINGBUILDING CONSTRUCTION ENTIRE COUNTY, EXCLUDING THE TOWNS OF PHELPS, SENECA AND GENEVA | $30.05 | $22.19 | NY20260030 |
| CEMENT MASONSHEAVY/HIGHWAY CONSTRUCTION (ROCHESTER CHAPTER) | $38.63 | $25.05 | NY20260030 |
| ELECTRICIAN | $44.30 | $30.20 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $31.72 | $29.87 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY B | $42.29 | $30.66 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY | $42.29 | $30.66 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMP | $47.57 | $31.03 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTIONLIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFOR | $52.86 | $35.60 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Substation:) | $63.14 | $33.82 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Substation:) | $35.34 | $30.12 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONFLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONGROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONLINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Substation:) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONMECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN, LINE CONSTRUCTIONCABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION ANDMAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITE | $61.56 | $36.21 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATIONGROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARYINSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRE | $49.25 | $31.15 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTINSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTGROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | NY20260030 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENTCABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | NY20260030 |
| ELEVATOR MECHANIC FOOTNOTEA.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $61.52 | $38.44 | NY20260030 |
| GLAZIER | $31.05 | $31.55 | NY20260030 |
| HAZARDOUS MATERIAL HANDLER(DUTIES LIMITED TO PREPARATION; WETTING; STRIPPING; REMOVAL; SCRAPPING; VACUUMING; BAGGING; AND DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY CONTAIN ASBESTOS OR NOT, FROM MECHANICAL SYSTEMS) | $40.26 | $25.41 | NY20260030 |
| IRONWORKERSSHEETER (REMAINDER OF COUNTY) | $36.00 | $30.80 | NY20260030 |
| IRONWORKERSSTRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER-RIGGER, FENCE ERECTOR PRECAST CONCRETE ERECTOR, REINFORCING, STONE DERRICKMAN (REMAINDER OF COUNTY) | $35.75 | $30.80 | NY20260030 |
| LABORERSGROUP 4 (HEAVY/HIGHWAY) BLASTERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $34.69 | $25.30 | NY20260030 |
| LABORERSGROUP 5 (HEAVY/HIGHWAY) HAZARDOUS WASTE REMOVAL FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.44 | $25.30 | NY20260030 |
| LABORERSGROUP 3 (HEAVY/HIGHWAY) RAKERS, DRILLERS, PIPELAYERS, AND TORCH OPERATORS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $33.86 | $25.30 | NY20260030 |
| LABORERSGROUP 2 (HEAVY/HIGHWAY) LABORERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $33.66 | $25.30 | NY20260030 |
| LABORERSGROUP 1 (HEAVY/HIGHWAY) FLAGGERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $32.96 | $25.30 | NY20260030 |
| OPERATING ENGINEERGROUP 7 (HEAVY AND HIGHWAY) MASTER MECHANIC FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $56.81 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 1 (EXCAVATING AND PAVING) ASPHALT PAVER; AUTOMATIC FINE GRADER; BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED); BLACKTOP PLANT (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX CONCRETE PLANT (AUTOMATED); CHERRY PICKER- OVER 5 TON CAPACITY; CRANE; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DUAL DRUM PAVER; FRONT END LOADER (4 CU. YD. AND OVER); HOIST,(TOW OR 3 DRUM); PILE DRIVER; POWER GRADER WITH ELEVATION LOADER ATTACHMENT; QUARRY MASTER (OR EQUIVALENT); SHOVEL; SLIP FORM PAVER; TRA | $41.26 | $34.85 | NY20260030 |
| OPERATING ENGINEERGROUP 1 (HEAVY AND HIGHWAY) AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT); AUTOMATED FINE GRADE MACHINE (CMI); BACKHOE; BELT PLACER (CMI OR SIMILAR); BLACKTOP SPREADER (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX PLANT (AUTOMATED); CHERRY PICKER (5 TONS); CONCRETE CURB MACHINE (SELF-PROPELLED SLIPFORM); CONCRETE PUMP; CRANE; CRANE SHAFT; CRANE UNDERGROUND; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DREDGE; DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILA | $55.38 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 1 (TUNNEL AND SHAFT) AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT); AUTOMATED FINE GRADE MACHINE (CMI); BACKHOE; BELT PLACER (CMI OR SIMILAR); BLACKTOP SPREADER (AUTOMATED); CABLEWAY; CAISSON AUGER; CENTRAL MIX PLANT (AUTOMATED); CHERRY PICKER (5 TONS); CONCRETE CURB MACHINE (SELF-PROPELLED SLIPFORM); CONCRETE PUMP; CRANE; CRANE SHAFT; CRANE UNDERGROUND; CRANES AND DERRICKS (STEEL ERECTION); DRAGLINE; DREDGE; DUAL DRUM PAVER; EXCAVATOR (ALL PURPOSE-HYDRAULICLY OPERATED GRADALL OR SIMILAR | $58.43 | $35.00 | NY20260030 |
| OPERATING ENGINEERGROUP 2 (EXCAVATING AND PAVING) BACKHOE (TRACTOR MOUNTED, RUBBER TIRED); BITUMINOUS SPREADER AND MIXER; BLACKTOP PLANT (NON AUTOMATED); BORING MACHINE; CAGE HOIST; CENTRAL MIX PLANT (NON AUTOMATED) AND ALL CONCRETE BATCHING PLANTS; CHERRY PICKER, 5 TONS AND UNDER; COMPRESSOR (4 OR LESS) EXCEEDING 2000 CFM COMBINED CAPACITY; CONCRETE PAVER OVER 16S; CONCRETE PUMP; CRUSHER; DRILL RIGS (TRACTOR MOUNTED); FRONT END LOADER (UNDER 4 CU. YDS); HI- PRESSURE BOILER (15 LBS AND OVER); HOIST (ONE DRUM); KO | $40.79 | $34.85 | NY20260030 |
| OPERATING ENGINEERGROUP 2 (HEAVY AND HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDE | $54.68 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 2 (TUNNEL AND SHAFT): AUTOMATED CENTRAL MIX CONCRETE PLANT; BACKHOE (TOPSIDE); BACKHOE (TRACTOR MOUNTED,RUBBER TIRED); BITUMINOUS SPREADER AND MIXER; BLACKTOP PLANT (NON AUTOMATED); BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED); BORING MACHINE; CAGE HOIST; CENTRAL MIX PLANT (NON AUTOMATED) AND ALL CONCRETE BATCHING PLANTS; CHERRY PICKER (5 TONS CAPACITY AND UNDER); COMPRESSORS (4 OR LESS EXCEEDING 2000 CFM COMBINED CAPACITY); CONCRETE PAVER (OVER 16S); CONCRETE PUMP; CRANE (TOPSIDE); CR | $57.21 | $35.00 | NY20260030 |
| OPERATING ENGINEERGROUP 3 (EXCAVATING AND PAVING) COMPRESSORS (4 NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR 3 OR LESS WITH MORE THAN 1200 CFM BUT NOT TO EXCEED 2000 CFM); COMPRESSORS (ANY SIZE BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS); DUST COLLECTORS; GENERATORS; WELDING MACHINES (4 OF ANY TYPE OR COMBINATION); CONCRETE PAVEMENT SPREADERS AND FINISHERS; CONVEYOR; DRILL (CORE); DRILL (WELL); ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS; FARM TRACTOR WITH ACCESSORIES; FINE GRADE MACHINE; FORK | $40.10 | $34.85 | NY20260030 |
| OPERATING ENGINEERGROUP 3 (HEAVY AND HIGHWAY): A FRAME WINCH HOIST ON TRUCK , ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-ON BOILER (USED IN CONJUNCTION WITH PRODUCTION), BITUMINOUS HEATER, SELF-PROPELLED, BOAT (POWERED), CEMENT AND BIN OPERATOR, COMPRESSORS, DUST COLLECTORS, GENERATORS, PUMPS, WELDING MACHINES, LIGHT PLANTS, HEATERS (HANDS-OFF EQUIPMENT), CONCRETE PAVEMENT SPREADER AND FINISHER, CONCRETE PAVER OR MIXER (16S AND UNDER), CONCR | $51.81 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 3 (TUNNEL AND SHAFT): ""A"" FRAME TRUCK; BALLAST REGULATOR (RIDE ON); COMPRESSORS (4 NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR 3 OR LESS WITH MORE THAN 1200 CFM BUT NOT TO EXCEED 2000 CFM); COMPRESSORS (ANY SIZE BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS; DUST COLLECTORS; GENERATORS; PUMPS; WELDING MACHINES; LIGHT PLANTS (4 OF ANY TYPE OR COMBINATION); CONCRETE PAVEMENT SPREADERS AND FINISHERS; CONVEYOR; DRILL (CORE); DRILL (WELL); ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT | $54.42 | $35.00 | NY20260030 |
| OPERATING ENGINEERGROUP 4 (EXCAVATING AND PAVING) COMPRESSOR (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS); DUST COLLECTORS; GENERATORS; WELDING MACHINES (3 OR LESS OF ANY TYPE OR COMBINATION); CONCRETE MIXER (16S AND UNDER), CONCRETE SAW-SELF PROPELLED; FIREMAN; FORM TAMPER; MULCHING MACHINE; POWER HEATERMAN; PUMPS REGARDLESS OF MOTIVE POWER NO MORE THAN 3 IN NUMBER NOT TO EXCEED 12"" IN TOTAL CAPACITY; REVINIUS WIDENER; STEAM CLEANER; TRACTOR FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DA | $36.61 | $34.85 | NY20260030 |
| OPERATING ENGINEERGROUP 4 (HEAVY AND HIGHWAY)TOWER CRANES FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $61.38 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 4 (TUNNEL AND SHAFT): CRANE, FRICTION OR LATTICE TYPE WITH BOOM LENGTH 200 FEET AND OVER FOOTNOTE: B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $51.41 | $35.00 | NY20260030 |
| OPERATING ENGINEERGROUP 5 (HEAVY AND HIGHWAY) GROUP 5: CRANES 50 TONS AND OVER FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $59.88 | $35.75 | NY20260030 |
| OPERATING ENGINEERGROUP 6 (HEAVY AND HIGHWAY) CRANES 49 TONS AND FOOTNOTE: B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $58.38 | $35.75 | NY20260030 |
| OPERATING ENGINEERMASTER MECHANIC (EXCAVATING AND PAVING). FOR EXCAVATION AND PAVING: FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | $43.26 | $34.85 | NY20260030 |
| OPERATING ENGINEERMASTER MECHANIC (TUNNEL AND SHAFT). FOR EXCAVATION AND PAVING: FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, REGARDLESS OF THE DAY OF THE WEEK ON WHICH THE HOLIDAY MAY FALL, PROVIDED THE EMPLOYEE WORKS EITHER ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY. EXCAVATION AND PAVING CLASSIFICATIONS | $60.84 | $35.00 | NY20260030 |
| PAINTERSBRIDGES, HEAVY & HIGHWAY CONSTRUCTION | $42.06 | $30.59 | NY20260030 |
| PAINTERSDRYWALL TAPER (BUILDING CONSTRUCTION) | $28.02 | $26.23 | NY20260030 |
| PAINTERSSANDBLASTING (BUILDING CONSTRUCTION) | $27.77 | $26.23 | NY20260030 |
| PAINTERSBRUSH & ROLL (BUILDING CONSTRUCTION) | $27.27 | $26.23 | NY20260030 |
| PAINTERSWALLCOVERING (BUILDING CONSTRUCTION) | $28.02 | $26.23 | NY20260030 |
| PAINTERSSPRAY (BUILDING CONSTRUCTION) | $27.77 | $26.23 | NY20260030 |
| PLUMBER AND STEAMFITTER | $42.68 | $27.88 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 1 (BUILDING CONSTRUCTION) AIR TUGGER, ALL TERRAIN TELESCOPING MATERIAL HANDLER, CLAMSHELL, DRAGLINE, SHOVEL AND SIMILAR MACHINES OVER THREE EIGHTHS CU.YD. CAPACITY (FACT. RATING);CARRIER MOUNTED BACKHOES THAT SWING 360 DEGREES BIG GENERATOR PLANT HOIST (ON STEEL ERECTION) BRIDGE CRANE (ALL TYPES), CABLEWAY, CAISSON AUGER AND SIMILAR TYPE MACHINE, CRANE, DERRICK, DREDGE, EXCAVATOR ALL PURPOSE HYDRAULICALLY OPERATED, FORKLIFT (WITH FACTORY RATING OF FIFTEEN FT. OR MORE OF LIFT),HOIST (ON STE | $43.14 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 8 (BUILDING CONSTRUCTION) TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $50.14 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 7 (BUILDING CONSTRUCTION) CRANES 251 AND OVER TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $50.64 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 6 (BUILDING CONSTRUCTION) CRANES 25-250 TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $49.64 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 5 (BUILDING CONSTRUCTION) CRANES UP TO AND INCLUDING 25 TONS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $47.64 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 4 (BUILDING CONSTRUCTION) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ON THE WORK DAY IMMEDIATELY PRECEDING THE HOLIDAY OR ON THE SCHEDULED WORK DAY IMMEDIATELY FOLLOWING THE HOLIDAY | $39.64 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 3 (BUILDING CONSTRUCTION) ANY COMBINATION (NOT TO EXCEED THREE (3) PIECES OF EQUIPMENT) COMPRESSORS �THREE (3) OR LESS, OR NOT TO EXCEED 1200 CFM COMBINED CAPACITY, FIREMAN, LONGITUDINAL FLOAT, MECHANICAL HEATER PUMPS (REGARDLESS OF MOTIVE POWER) NO MORE THAN THREE (3) IN NUMBER, NOT TO EXCEED TWELVE (12) INCHES TOTAL CAPACITY, ROLLER (FILL AND GRADE)RUBBER TIRED TRACTOR WELDING MACHINE OR MECHANICAL CONVEYOR (OVER 12FT. IN LENGTH) EXCEPTION: SINGLE GASOLINE DRIVEN WELDING MACHINE UP TO 30 | $39.64 | $35.20 | NY20260030 |
| POWER EQUIPMENT OPERATORSGROUP 2 (BUILDING CONSTRUCTION) A-FRAME TRUCK, BACKFILLING MACHINE, BACKHOE -TRACTOR MOUNTED, BARBER GREEN AND SIMILAR TYPE MACHINES, BELT CRETE AND SIMILAR TYPE MACHINES, BITUMINOUS SPREADING MACHINE 3/8 YD. CAPACITY OR LESS(FACTORY RATING), BULLDOZER, CARRY-ALL TYPE SCRAPER, COMPRESSORS: FOUR (4) NOT TO EXCEED 2000 CFM COMBINED CAPACITY; OR THREE (3) OR LESS WITH MORE THAN1200 CFM BUT NOT TO EXCEED 2000 CFM, CONCRETE MIXER, CONCRETE PLACER, CONCRETE PUMP, DINKY LOCOMOTIVES (ALL TYPES), ELEVATI | $42.34 | $35.20 | NY20260030 |
| ROOFER | $34.10 | $28.20 | NY20260030 |
| SHEET METAL WORKER | $43.01 | $28.66 | NY20260030 |
| SPRINKLER FITTER | $47.85 | $28.94 | NY20260030 |
| TRUCK DRIVERSGROUP 3 SEMI-TRAILERS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC; FUEL TRUCK. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | $31.49 | $27.77 | NY20260030 |
| TRUCK DRIVERSGROUP 4 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE UNIT. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | $31.64 | $27.77 | NY20260030 |
| TRUCK DRIVERSGROUP 5 OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE-HITCHED EQUIPMENT SHERE NOT SELF-LOADED. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | $31.79 | $27.77 | NY20260030 |
| TRUCK DRIVERSGROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | $31.39 | $27.77 | NY20260030 |
| TRUCK DRIVERSGROUP 2 TANDEMS; BATCH TRUCK; MECHANICS. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY | $31.44 | $27.77 | NY20260030 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.