ELECTRICIAN leads the heavy schedule for Passaic County, NJ at $71.97 base plus $46.42 fringe. The active federal wage determination covering heavy construction in Passaic County, NJ lists 24 classifications with published rates, base pay from $24.05 to $71.97 per hour. The determination was last modified May 18, 2026.
Classifications
24
with published rates
Median base
$52.13
per hour
Median fringe
66%
of base pay
Last modified
May 18, 2026
Published rates
Classification
Base
Fringe
WD
CARPENTERINCLUDING FORM WORK THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER
CARPENTER DOCK BUILDER(All other Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hour ad
The highest published base on this schedule belongs to ELECTRICIAN at $71.97 per hour plus $46.42 fringe; the schedule's median base is $52.13.
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
92% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
Using these rates
Read the modification number
A wage determination is cited as number plus modification, for example NJ20260061 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Put the WD in your bid file
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
Check rates the Friday before payroll
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
Match classifications by duties, not titles
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
Fringe crediting basics
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
Statement of Compliance wording
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Questions
Which wage determination applies to my project in Passaic County?
The wage determination incorporated into your contract is the one that governs, per 29 CFR 1.6. For new heavy work in Passaic County, NJ, the current active determination is NJ20260061. Verify with your contracting officer before bidding or paying.
How often do these rates change?
DOL publishes wage determination modifications weekly, generally on Fridays. The determination behind this page was last modified May 18, 2026.
What is the difference between the base rate and the fringe rate?
The base rate is the minimum hourly wage; the fringe amount is an additional hourly benefit obligation you can meet with bona fide benefit contributions or pay in cash. On this schedule the median fringe is about 66% of base.
My classification is not listed for Passaic County. What do I do?
If the work classification you need is not on the determination, the contractor requests a conformance (additional classification and rate) through the contracting agency using Standard Form 1444. Do not substitute a similar-sounding classification.
What counts as heavy construction?
Heavy covers projects that are not building, residential, or highway, such as water and sewer lines, dams, and flood control. Agencies sometimes split it further; the contract states which schedule applies.
Does the federal rate or the New Jersey state prevailing wage apply?
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
(Concrete form Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hou
ELECTRICIAN(CABLE SPLICER) WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE
ELECTRICIAN WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING(DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE
LABORERLANDSCAPE LABORER, POWER TOOL OPERATOR HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENT
MILLWRIGHT Work of erection and dismantling of elevators and towers, such asconcrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.
POWER EQUIPMENT OPERATORSGROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER W
POWER EQUIPMENT OPERATORSGROUP 4 BROOM; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); ROLLER, GRADE; PUMP HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL EL
POWER EQUIPMENT OPERATORSGROUP 3 ASPHALT SPREADER; BULLDOZER; COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); CRUSHER; FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.
POWER EQUIPMENT OPERATORSGROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON
POWER EQUIPMENT OPERATORSGROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE) HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE
TRUCK DRIVEROFF THE ROAD TRUCK; PICKUP TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A TRUCK DRIVER: OFF THE ROAD TRUCK; PICKUP TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL B, C OR D PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS BEEN ASSIGNED TO WORK, OR, ""SHAPES"", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS
TRUCK DRIVERDUMP TRUCK; FLATBED TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OTRUCK DRIVER: DUMP TRUCK; FLATBED TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL B, C OR D PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $1.00 PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS BEEN ASSIGNED TO WORK, OR, ""SHAPES"", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.
They are separate systems. Davis-Bacon rates apply to federally funded or assisted work; a state prevailing wage law can apply to state-funded work. A project can be covered by both, in which case the higher rate for each classification effectively controls. This page shows the federal determination only.
Is the WH-347 form mandatory?
The WH-347 itself is optional; what is mandatory on covered work is submitting weekly certified payroll with the same information and a signed Statement of Compliance. Most contractors use the WH-347 layout because agencies expect it.