PLUMBER, EXCLUDES HVAC PIPE INSTALLATION leads the building schedule for Miller County, MO at $58.38 base plus $25.29 fringe. The active federal wage determination covering building construction in Miller County, MO lists 52 classifications with published rates, base pay from $18.79 to $58.38 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR(DENT, GASCONADE, MARIES & MONTGOMERY COUNTIES) | $43.48 | $27.24 | MO20260033 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR(MILLER & MORGAN COUNTIES) | $31.97 | $14.00 | MO20260033 |
| BRICKLAYER | $27.66 | $5.88 | MO20260033 |
| CARPENTERINCLUDING DRYWALL HANGING, FORM WORK & RESILIENT/VINYL FLOOR INSTALLATION (MILLER & MORGAN COUNTIES) |
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
With 52 classifications carrying published rates, this is a comparatively deep schedule; most trades a building project needs appear without a conformance request.
88% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
A wage determination is cited as number plus modification, for example MO20260033 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| $31.51 |
| $22.25 |
| MO20260033 |
| CARPENTERINCLUDING DRYWALL HANGING & FORM WORK (DENT, GASCONADE & MARIES COUNTIES) | $44.19 | $21.85 | MO20260033 |
| CARPENTER(FLOOR LAYER): RESILIENT & VINYL FLOORING ONLY (DENT, GASCONADE, MARIES & MONTGOMERY COUNTIES) | $40.08 | $21.85 | MO20260033 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK(MONTGOMERY COUNTY) (Projects under $1 million) | $39.53 | $21.85 | MO20260033 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK(MONTGOMERY COUNTY) (Projects $1 million and over) | $41.30 | $21.85 | MO20260033 |
| CEMENT MASON/CONCRETE FINISHER(GASCONADE, MARIES, MILLER, MONTGOMERY, & MORGAN COUNTIES) | $33.52 | $15.88 | MO20260033 |
| CEMENT MASON/CONCRETE FINISHER(DENT COUNTY) | $36.63 | $9.85 | MO20260033 |
| ELECTRICIAN(MORGAN COUNTY) | $54.01 | $27.85 | MO20260033 |
| ELECTRICIAN(DENT, GASCONADE, MARIES, & MILLER COUNTIES) | $40.50 | $23.26 | MO20260033 |
| ELECTRICIAN(MONTGOMERY COUNTY) | $37.60 | $22.14 | MO20260033 |
| GLAZIER | $29.87 | $1.47 | MO20260033 |
| IRONWORKER, REINFORCING | $21.02 | $9.49 | MO20260033 |
| IRONWORKER, STRUCTURAL(MORGAN COUNTY) | $36.00 | $34.25 | MO20260033 |
| IRONWORKER, STRUCTURAL(DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $41.67 | $31.25 | MO20260033 |
| LABORERCOMMON OR GENERAL, LANDSCAPE & BRICK MASON TENDER (MONTGOMERY COUNTY) | $41.18 | $15.96 | MO20260033 |
| LABORERBRICK MASON TENDER (MORGAN COUNTY) | $28.95 | $14.95 | MO20260033 |
| LABORERCOMMON OR GENERAL & LANDSCAPE (MORGAN COUNTY) | $26.95 | $14.95 | MO20260033 |
| LABORERBRICK MASON TENDER (DENT, GASCONADE & MARIES COUNTIES) | $32.23 | $15.91 | MO20260033 |
| LABORERCOMMON OR GENERAL & LANDSCAPE (DENT, GASCONADE & MARIES COUNTIES) | $30.33 | $15.91 | MO20260033 |
| LABORERCOMMON OR GENERAL & LANDSCAPE (MILLER COUNTY) | $27.71 | $15.50 | MO20260033 |
| LABORERBRICK MASON TENDER (MILLER COUNTY) | $29.71 | $15.50 | MO20260033 |
| LABORERASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, & CEILINGS) | $24.90 | $0.00 | MO20260033 |
| PAINTERBRUSH & ROLLER ONLY (MORGAN COUNTY) | $24.43 | $17.76 | MO20260033 |
| PAINTERDRYWALL FINISHING/TAPING ONLY (MORGAN COUNTY) | $25.39 | $17.76 | MO20260033 |
| PAINTERBRUSH, ROLLER, & DRYWALL FINISHING/TAPING ONLY (GASCONADE & MONTGOMERY COUNTIES) | $28.56 | $17.21 | MO20260033 |
| PAINTERBRUSH & ROLLER ONLY (DENT, MARIES, & MILLER COUNTIES) | $33.90 | $17.21 | MO20260033 |
| PAINTERDRYWALL FINISHING/TAPING ONLY (DENT, MARIES, & MILLER COUNTIES) | $34.90 | $17.21 | MO20260033 |
| PAINTERSPRAY | $18.79 | $8.12 | MO20260033 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION(MORGAN COUNTY) | $57.51 | $28.35 | MO20260033 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATIONMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $48.66 | $30.13 | MO20260033 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATIONMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $50.60 | $29.38 | MO20260033 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION(MORGAN COUNTY) | $58.38 | $25.29 | MO20260033 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATIONMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $48.66 | $30.13 | MO20260033 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATIONMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $50.60 | $29.38 | MO20260033 |
| POWER EQUIPMENT OPERATORROLLER | $35.76 | $30.38 | MO20260033 |
| POWER EQUIPMENT OPERATOR(LOADER) | $39.06 | $30.38 | MO20260033 |
| POWER EQUIPMENT OPERATORGRADER/BLADE | $39.06 | $30.38 | MO20260033 |
| POWER EQUIPMENT OPERATORBULLDOZER | $39.06 | $30.38 | MO20260033 |
| POWER EQUIPMENT OPERATOR(BACKHOE/EXCAVATOR/ TRACKHOE) | $39.06 | $30.38 | MO20260033 |
| POWER EQUIPMENT OPERATOR(PAVER) | $39.06 | $30.38 | MO20260033 |
| ROOFER(GASCONADE & MONTGOMERY COUNTIES) | $40.00 | $22.05 | MO20260033 |
| ROOFER(DENT COUNTY) | $32.25 | $17.46 | MO20260033 |
| ROOFER(MARIES, MILLER, & MORGAN COUNTIES) | $33.60 | $19.99 | MO20260033 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION(MILLER & MORGAN COUNTIES) | $47.20 | $26.28 | MO20260033 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION(DENT, GASCONADE, & MONTGOMERY COUNTIES) | $52.00 | $27.12 | MO20260033 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION(MARIES COUNTY) | $36.51 | $22.39 | MO20260033 |
| SPRINKLER FITTER(FIRE SPRINKLERS) | $45.94 | $27.53 | MO20260033 |
| TILE SETTER | $32.79 | $21.31 | MO20260033 |
| TRUCK DRIVERDUMP TRUCK | $25.57 | $0.00 | MO20260033 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.