PLUMBER leads the residential schedule for Jefferson County, MO at $52.60 base plus $29.93 fringe. The active federal wage determination covering residential construction in Jefferson County, MO lists 30 classifications with published rates, base pay from $16.00 to $52.60 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| BRICKLAYER | $41.15 | $23.90 | MO20260070 |
| CARPENTER, INCLUDES DRYWALL HANGING(JEFERSON, LINCOLN, ST CHARLES, ST LOUIS, WARREN & WASHINGTON COUNTIES) | $36.90 | $21.55 | MO20260070 |
| CARPENTER, INCLUDES DRYWALL HANGING(CRAWFORD COUNTY) | $32.38 | $21.55 | MO20260070 |
| CEMENT MASON/CONCRETE FINISHER | $16.00 | $0.00 |
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
With 30 classifications carrying published rates, this is a comparatively deep schedule; most trades a residential project needs appear without a conformance request.
97% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
A wage determination is cited as number plus modification, for example MO20260070 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| MO20260070 |
| ELECTRICIAN(REMAINDER OF COUNTIES) | $44.36 | $11.53 | MO20260070 |
| ELECTRICIAN(CRAWFORD COUNTY) | $18.23 | $9.91 | MO20260070 |
| LABORERCOMMON OR GENERAL (ST LOUIS COUNTY) | $31.57 | $15.85 | MO20260070 |
| LABORERGENERAL LABOR (JEFFERSON COUNTY) | $30.37 | $15.91 | MO20260070 |
| LABORERGENERAL LABORER (WASHINGTON COUNTY) | $30.37 | $15.91 | MO20260070 |
| LABORERMASON TENDER - BRICK ST. CHARLES COUNTY | $40.26 | $16.05 | MO20260070 |
| LABORERMASON TENDER - BRICK LINCOLN AND WARREN COUNTIES | $40.26 | $16.05 | MO20260070 |
| LABORERCOMMON OR GENERAL ST.CHARLES COUNTY | $34.07 | $14.85 | MO20260070 |
| LABORERCOMMON OR GENERAL LINCOLN AND WARREN COUNTIES | $33.57 | $14.85 | MO20260070 |
| LABORERCOMMON OR GENERAL (CRAWFORD COUNTY) | $25.84 | $14.86 | MO20260070 |
| LABORERMASON TENDER - BRICK (CRAWFORD COUNTY) | $25.84 | $14.86 | MO20260070 |
| PAINTERDRYWALL FINISHING/TAPING (JEFFERSON, LINCOLN, ST CHARLES, ST LOUIS, WARREN AND WASHINGTON COUNTIES) | $38.60 | $17.66 | MO20260070 |
| PAINTERBRUSH & ROLLER (JEFFERSON, LINCOLN, ST CHARLES, ST LOUIS, WARREN AND WASHINGTON COUNTIES) | $38.60 | $17.66 | MO20260070 |
| PAINTERSDRYWALL FINISHING/TAPING (CRAWFORD COUNTY) | $34.90 | $17.21 | MO20260070 |
| PAINTERSBRUSH AND ROLLER (CRAWFORD COUNTY) | $33.90 | $17.21 | MO20260070 |
| PLUMBERMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (CRAWFORD, LINCOLN, WARREN, & WASHINGTON COUNTIES) | $50.60 | $29.38 | MO20260070 |
| PLUMBERMECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (CRAWFORD, LINCOLN, WARREN, & WASHINGTON COUNTIES) | $50.60 | $29.38 | MO20260070 |
| PLUMBER(JEFFERSON, ST CHARLES, AND ST LOUIS COUNTIES) | $52.60 | $29.93 | MO20260070 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR (CRAWFORD & WASHINGTON COUNTIES) | $34.61 | $29.50 | MO20260070 |
| POWER EQUIPMENT OPERATOR: ROLLER (CRAWFORD & WASHINGTON COUNTIES) | $34.61 | $29.50 | MO20260070 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR (JEFFERSON, LINCOLN, ST CHARLES, ST LOUIS & WARREN COUNTIES) | $41.01 | $29.63 | MO20260070 |
| POWER EQUIPMENT OPERATOR: ROLLER (JEFFERSON, LINCOLN, ST CHARLES, ST LOUIS & WARREN COUNTIES) | $41.01 | $29.63 | MO20260070 |
| ROOFER | $40.00 | $22.05 | MO20260070 |
| SHEET METAL WORKER(INCLUDING INSTALLATION OF HVAC DUCT AND HVAC SYSTEM) | $52.00 | $27.12 | MO20260070 |
| SPRINKLER FITTER(FIRE SPRINKLERS) (JEFFERSON, ST CHARLES & ST LOUIS COUNTIES) | $52.32 | $28.96 | MO20260070 |
| SPRINKLER FITTER(FIRE SPRINKLERS) (CRAWFORD, LINCOLN, WARREN & WASHINGTON COUNTIES) | $42.93 | $27.52 | MO20260070 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.