ELEVATOR MECHANIC FOOTNOTES leads the building schedule for Livingston County, MI at $65.45 base plus $38.44 fringe. The active federal wage determination covering building construction in Livingston County, MI lists 64 classifications with published rates, base pay from $13.57 to $65.45 per hour. The determination was last modified May 18, 2026.
| Classification | Base | Fringe | WD |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 | MI20260090 |
| BOILERMAKER | $43.50 | $36.74 | MI20260090 |
| BRICKLAYER(TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $36.10 | $26.22 | MI20260090 |
| BRICKLAYER(TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR |
The highest published base on this schedule belongs to ELEVATOR MECHANIC FOOTNOTES at $65.45 per hour plus $38.44 fringe; the schedule's median base is $36.83.
The most recent modification to the governing determination is dated May 18, 2026. DOL's weekly publication cycle means further modifications can post on any Friday.
92% of the rate lines here carry union local identifiers, so the published figures track negotiated agreements, which is why some classifications carry high fringe amounts relative to base.
A wage determination is cited as number plus modification, for example MI20260090 Mod dated May 18, 2026. Your certified payroll should reflect the determination in your contract, not necessarily the newest one.
Save the full determination text with your bid papers the day you price the job. If rates change later, the contract determination is your record of what you bid against.
DOL publishes modifications weekly, generally Fridays. A quick check before running payroll catches a mid-project modification before it shows up in an agency review instead.
The classification that applies is determined by the work performed, not the worker's title. A foreman who works with the tools is generally due the rate for the hours on the tools.
You can meet the fringe obligation with bona fide benefit plan contributions, cash, or a combination. Track the hourly equivalent of what you contribute; agencies ask for the math.
The signed Statement of Compliance may be the WH-347 back page or another document with identical wording. The signature is a federal certification by your company's officer; accuracy is on the certifier.
Synced from SAM.gov July 18, 2026. The wage determination incorporated into your contract is the legally operative document.
| $40.71 |
| $28.21 |
| MI20260090 |
| CARPENTERINCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING (REMAINDER OF COUNTY) | $42.44 | $31.43 | MI20260090 |
| CARPENTERINCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO & MARION) | $36.21 | $21.06 | MI20260090 |
| CARPENTERFLOOR LAYER - CARPET, RESILIENT & VINYL FLOORING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO & MARION) | $36.21 | $21.06 | MI20260090 |
| CARPENTERFLOOR LAYER - CARPET, RESILIENT, & VINYL FLOORING (REMAINDER OF COUNTY) | $36.76 | $21.11 | MI20260090 |
| CEMENT MASON/CONCRETE FINISHER(TOWNSHIPS OF DEERFIELD, HARTLAND, OSCEOLA AND TYRONE:) | $25.58 | $12.88 | MI20260090 |
| CEMENT MASON/CONCRETE FINISHER(TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL AND THE ENTIRE CITY OF HOWELL) | $24.64 | $12.88 | MI20260090 |
| CEMENT MASON/CONCRETE FINISHER(REMAINDER OF COUNTY) | $32.23 | $22.11 | MI20260090 |
| ELECTRICIANLOW VOLTAGE WIRING & ALARM INSTALLATION (TOWNSHIPS OF BRIGHTON, DEERFIELD, GENOA, HARTLAND, OCEOLA & TYRONE) | $36.89 | $14.16 | MI20260090 |
| ELECTRICIANALARM INSTALLATION & LOW VOLTAGE WIRING (TOWNSHIPS OF GREEN OAK, HAMBURG, PUTNAM AND UNADILLA) | $38.79 | $19.87 | MI20260090 |
| ELECTRICIANALARM INSTALLATION & LOW VOLTAGE WIRING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO AND MARION) | $31.20 | $10.97 | MI20260090 |
| ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING FOR AND INSTALLATION OF ALARMS | $28.14 | $8.89 | MI20260090 |
| ELEVATOR MECHANIC FOOTNOTESA. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OF 6% BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF SERVICE AS VACATION PAY CREDIT | $65.45 | $38.44 | MI20260090 |
| GLAZIER(EASTERN HALF INCLUDING THE CITY OF HOWELL) PAID HOLIDAYS: NEW YEAR'S DAY, DECORATION DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS WORKED THE LAST FULL REGULAR SCHEDULED WORK DAY PRIOR TO THE HOLIDAY, AND THE FIRST FULL REGULAR SCHEDULED WORK DAY FOLLOWING THE HOLIDAY, PROVIDED THE EMPLOYEE IS PHYSICALLY ABLE TO WORK | $42.00 | $25.55 | MI20260090 |
| GLAZIER(WESTERN HALF INCLUDING THE CITY OF HOWELL) | $37.41 | $18.99 | MI20260090 |
| INSTALLER - OVERHEAD DOOR | $27.98 | $0.00 | MI20260090 |
| IRONWORKERREINFORCING | $36.55 | $33.37 | MI20260090 |
| IRONWORKERSTRUCTURAL | $36.55 | $35.93 | MI20260090 |
| IRONWORKER, ORNAMENTAL | $18.48 | $7.93 | MI20260090 |
| IRONWORKER STRUCTURAL(METAL BUILDING ERECTION ONLY) (WEST OF BURKHARDT ROAD) | $30.02 | $27.43 | MI20260090 |
| IRONWORKER STRUCTURAL(METAL BUILDING ERECTION ONLY) (EAST OF BURKHARDT ROAD) | $30.02 | $27.43 | MI20260090 |
| LABORERASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS & CEILINGS) | $39.08 | $15.92 | MI20260090 |
| LABORERLANDSCAPE & IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 | MI20260090 |
| LABORERLANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 | MI20260090 |
| LABORERMASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.33 | $15.45 | MI20260090 |
| LABORERCOMMON OR GENERAL; GRADE CHECKER; SANDBLASTER (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.11 | $15.45 | MI20260090 |
| LABORERPIPELAYER (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.47 | $15.45 | MI20260090 |
| LABORERGRADE CHECKER; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; PIPELAYER; SANDBLASTER (WEST OF OAK GROVE ROAD TO WEST OF PINKNEY ROAD AND DEXTER PINKNEY ROAD, INCLUDING THE CITY OF HOWELL) | $32.53 | $13.45 | MI20260090 |
| LABORERGRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER; SANDBLASTER (EAST OF OAK GROVE RD. & NORTH OF M-59 (DOES NOT INCLUDE THE CITY OF HOWELL)) | $38.00 | $18.25 | MI20260090 |
| LABORERCOMMON OR GENERAL | $17.64 | $4.95 | MI20260090 |
| MILLWRIGHT | $42.92 | $39.13 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 5 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR/TRACKHOE; BULLDOZER; CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; LOADER; ROLLER; SCRAPER; STIFF LEG DERRICK; TRACTOR; TRENCHER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 | MI20260090 |
| OPERATORPOWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 | MI20260090 |
| PAINTERBRUSH AND ROLLER (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $32.85 | $20.41 | MI20260090 |
| PAINTERDRYWALL FINISHING/TAPING (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $32.85 | $20.41 | MI20260090 |
| PAINTERSPRAY (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $26.86 | $17.66 | MI20260090 |
| PAINTERDRYWALL FINISHING/TAPING (WEST OF THE EASTERN CITY LIMITS OF HOWELL, INCLUDING THE CITY OF HOWELL, NORTH TO THE GENESEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE) | $28.32 | $16.88 | MI20260090 |
| PAINTERBRUSH, ROLLER AND SPRAY (WEST OF THE EASTERN CITY LIMITS OF HOWELL, INCLUDING THE CITY OF HOWELL, NORTH TO THE GENESEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE) | $28.75 | $18.68 | MI20260090 |
| PIPEFITTEREXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) | $51.30 | $25.87 | MI20260090 |
| PIPEFITTEREXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE WORK DAY PRECEDING AND FOLLOWING THE HOLIDAY UNLESS PROVEN ILLNESS OR INJURY PREVENTS THE EMPLOYEE FROM WORKING | $46.29 | $25.43 | MI20260090 |
| PIPEFITTEREXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) | $40.30 | $38.80 | MI20260090 |
| PLASTERER(TOWNSHIPS OF COHOCTAH, CONWAY, HANDY & HOWELL) | $25.39 | $12.53 | MI20260090 |
| PLASTERER(TOWNSHIPS OF DEERFIELD, HARTLAND, OCEOLA & TYRONE) | $23.73 | $12.88 | MI20260090 |
| PLASTERER(EXCLUDING TOWNSHIPS OF COHOCTAH, CONWAY, DEERFIELD, HANDY, HARTLAND, HOWELL, OSCEOLA & TYRONE) | $30.63 | $14.07 | MI20260090 |
| PLUMBERINCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) | $43.34 | $32.92 | MI20260090 |
| PLUMBERINCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) | $51.30 | $25.87 | MI20260090 |
| PLUMBERINCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE WORK DAY PRECEDING AND FOLLOWING THE HOLIDAY UNLESS PROVEN ILLNESS OR INJURY PREVENTS THE EMPLOYEE FROM WORKING | $46.29 | $25.43 | MI20260090 |
| POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: GROUP 1 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $42.74 | $21.53 | MI20260090 |
| POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $42.74 | $21.53 | MI20260090 |
| ROOFER | $42.67 | $21.62 | MI20260090 |
| SPRINKLER FITTER(FIRE SPRINKLERS) | $41.34 | $27.39 | MI20260090 |
| TILE FINISHER(TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.50 | $23.52 | MI20260090 |
| TILE FINISHER(TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.50 | $23.52 | MI20260090 |
| TILE SETTER(TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $40.53 | $23.62 | MI20260090 |
| TILE SETTER(TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE) FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $40.53 | $23.62 | MI20260090 |
| TRUCK DRIVERTRACTOR HAUL TRUCK | $13.57 | $1.18 | MI20260090 |
* changed in the most recent modification. Survey-based (SU) identifiers are non-union survey rates. Amounts tagged per day or per shift are published that way in the source determination and are not hourly wages; they are excluded from the hourly figures above.